California By Sd construction progress

California By Sd in Discovery Gardens is 24% built at the Land Department inspection of September 2026. Developer Samana Si Holding Limited Dubai Branch.

24%

Built, at the Land Department site inspection of 28 September 2026

Finish at recent pace
March 2029
Construction started
December 2023
Registered with the Land Department
September 2023
Units
178
Escrow bank
Emirates NBD
Name in Arabic
Sd كاليفورنيا بواسطة
Land Department project number
2666
Land Department site inspections
6

Schedule

Since February 2026 California By Sd has added about 2.5 points a month. At that rate the site reaches 100% around March 2029. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

28 September 2026

24%+9.5 pts

  • California By Sd construction site, Land Department inspection photo 1, 28 September 2026
  • California By Sd construction site, Land Department inspection photo 2, 28 September 2026
  • California By Sd construction site, Land Department inspection photo 3, 28 September 2026
  • California By Sd construction site, Land Department inspection photo 4, 28 September 2026

17 June 2026

15%+9.7 pts

  • California By Sd construction site, Land Department inspection photo 1, 17 June 2026
  • California By Sd construction site, Land Department inspection photo 2, 17 June 2026
  • California By Sd construction site, Land Department inspection photo 3, 17 June 2026
  • California By Sd construction site, Land Department inspection photo 4, 17 June 2026

10 February 2026

5.4%+3.9 pts

  • California By Sd construction site, Land Department inspection photo 1, 10 February 2026
  • California By Sd construction site, Land Department inspection photo 2, 10 February 2026
  • California By Sd construction site, Land Department inspection photo 3, 10 February 2026
  • California By Sd construction site, Land Department inspection photo 4, 10 February 2026

11 September 2025

1.5%+0.4 pts

  • California By Sd construction site, Land Department inspection photo 1, 11 September 2025
  • California By Sd construction site, Land Department inspection photo 2, 11 September 2025
  • California By Sd construction site, Land Department inspection photo 3, 11 September 2025

6 February 2025

1.1%+1.1 pts

  • California By Sd construction site, Land Department inspection photo 1, 6 February 2025
  • California By Sd construction site, Land Department inspection photo 2, 6 February 2025
  • California By Sd construction site, Land Department inspection photo 3, 6 February 2025
  • California By Sd construction site, Land Department inspection photo 4, 6 February 2025

18 May 2023

0%

  • California By Sd construction site, Land Department inspection photo 1, 18 May 2023

All 24 site photos, by inspection date

Context

Discovery Gardens has 9 projects under construction, 46% built on average.

Samana Si Holding Limited Dubai Branch has 4 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in California By Sd?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will California By Sd be completed?
The Land Department has no completion date on record for California By Sd yet.
How much of California By Sd is built?
24%, measured at the Land Department site inspection on 28 September 2026. The Land Department engineers have inspected the site 6 times since May 2023.
Who is building California By Sd?
The registered developer is Samana Si Holding Limited Dubai Branch. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for California By Sd?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.