One Park Central By Iman construction progress
One Park Central By Iman in Jumeirah Village Circle is 20% built at the Land Department inspection of March 2026. Developer Iman Developers. Completion registered for June 2027.
20%
Built, at the Land Department site inspection of 11 March 2026
Running behind its date
- Completion date (Land Department)
- June 2027
- Finish at recent pace
- September 2030
- Construction started
- April 2024
- Registered with the Land Department
- June 2024
- Developer
- Iman Developers
- Community
- Jumeirah Village Circle
- Units
- 526
- Escrow bank
- Mashreq Bank
- Name in Arabic
- بارك سنترال باي ايمان 1
- Land Department project number
- 2969
- Land Department site inspections
- 5
Schedule
Between May 2025 and March 2026 the site added about 1.5 points a month. At that rate it would finish around September 2030, more than three months after the June 2027 date registered with the Land Department.
Site inspections
11 March 2026
20%+8.0 pts
24 December 2025
12%+6.0 pts
27 May 2025
6.1%+3.1 pts
23 December 2024
3.0%+3.0 pts
1 March 2024
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Iman Developers has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in One Park Central By Iman?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will One Park Central By Iman be completed?
- The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around September 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of One Park Central By Iman is built?
- 20%, measured at the Land Department site inspection on 11 March 2026. The Land Department engineers have inspected the site 5 times since March 2024.
- Is One Park Central By Iman delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building One Park Central By Iman?
- The registered developer is Iman Developers. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for One Park Central By Iman?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 10 Oxford By ImanAlso by Iman Developers. 91%.
- Gardens 2Also by Iman Developers. 68%, Due December 2025, passed.
- One Sky Park By ImanAlso by Iman Developers. 9.0%, Due March 2028.
- One Park Square By ImanAlso by Iman Developers. 20%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)