One Park Central By Iman construction progress

One Park Central By Iman in Jumeirah Village Circle is 20% built at the Land Department inspection of March 2026. Developer Iman Developers. Completion registered for June 2027.

20%

Built, at the Land Department site inspection of 11 March 2026

Running behind its date

Completion date (Land Department)
June 2027
Finish at recent pace
September 2030
Construction started
April 2024
Registered with the Land Department
June 2024
Units
526
Escrow bank
Mashreq Bank
Name in Arabic
بارك سنترال باي ايمان 1
Land Department project number
2969
Land Department site inspections
5

Schedule

Between May 2025 and March 2026 the site added about 1.5 points a month. At that rate it would finish around September 2030, more than three months after the June 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

11 March 2026

20%+8.0 pts

  • One Park Central By Iman construction site, Land Department inspection photo 1, 11 March 2026
  • One Park Central By Iman construction site, Land Department inspection photo 2, 11 March 2026
  • One Park Central By Iman construction site, Land Department inspection photo 3, 11 March 2026
  • One Park Central By Iman construction site, Land Department inspection photo 4, 11 March 2026

24 December 2025

12%+6.0 pts

  • One Park Central By Iman construction site, Land Department inspection photo 1, 24 December 2025
  • One Park Central By Iman construction site, Land Department inspection photo 2, 24 December 2025
  • One Park Central By Iman construction site, Land Department inspection photo 3, 24 December 2025

27 May 2025

6.1%+3.1 pts

  • One Park Central By Iman construction site, Land Department inspection photo 1, 27 May 2025
  • One Park Central By Iman construction site, Land Department inspection photo 2, 27 May 2025
  • One Park Central By Iman construction site, Land Department inspection photo 3, 27 May 2025

23 December 2024

3.0%+3.0 pts

  • One Park Central By Iman construction site, Land Department inspection photo 1, 23 December 2024
  • One Park Central By Iman construction site, Land Department inspection photo 2, 23 December 2024
  • One Park Central By Iman construction site, Land Department inspection photo 3, 23 December 2024
  • One Park Central By Iman construction site, Land Department inspection photo 4, 23 December 2024

1 March 2024

0%

  • One Park Central By Iman construction site, Land Department inspection photo 1, 1 March 2024
  • One Park Central By Iman construction site, Land Department inspection photo 2, 1 March 2024

All 22 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Iman Developers has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in One Park Central By Iman?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will One Park Central By Iman be completed?
The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around September 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of One Park Central By Iman is built?
20%, measured at the Land Department site inspection on 11 March 2026. The Land Department engineers have inspected the site 5 times since March 2024.
Is One Park Central By Iman delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building One Park Central By Iman?
The registered developer is Iman Developers. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for One Park Central By Iman?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.