Iman Developers projects under construction
Iman Developers has 10 projects under construction in Dubai. On average they are 24% built. 1 has passed its registered completion date. The next one due is One Park Central By Iman, in June 2027.
- 10 Oxford By ImanJumeirah Village Circle91%No date set
- Gardens 2Arjan68%Due December 2025, passed
- One Park Central By ImanJumeirah Village Circle32%Due June 2027
- One Sky Park By ImanJumeirah Village Circle22%Due March 2028
- One Park Square By ImanJumeirah Village Circle20%Due June 2028
- 15 CascadeMotor City5.5%Due September 2028
- Sierra By ImanMotor City3.7%Due June 2029
- 113 Residences0%Due February 2029
- Element By Iman0%Due December 2029
- Oxford Cove0%Due March 2029
Questions
How many projects is Iman Developers building in Dubai?
10 projects are under construction, 24% built on average at the latest site inspections.
Which Iman Developers projects finish next?
By registered completion date: One Park Central By Iman (June 2027, 32% built), One Sky Park By Iman (March 2028, 22% built) and One Park Square By Iman (June 2028, 20% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
Are any Iman Developers projects delayed?
1 of its 10 projects have passed the registered completion date, among them Gardens 2. A project counts as late once its registered completion date has passed before it reaches 100%.
Where is Iman Developers building?
Its projects are in Jumeirah Village Circle (4), Motor City (2) and Arjan (1).
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.