One Park Square By Iman construction progress

The registered completion date for One Park Square By Iman in Jumeirah Village Circle is June 2028. At the last site inspection, in September 2026, it was 20% built. The developer is Iman Developers.

20%

Built, at the site inspection of 22 September 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
September 2031
Construction started
January 2025
First registered
January 2025
Units
269
Escrow bank
Dubai Islamic Bank
Name in Arabic
وان بارك سكوير باي إيمان
Project number
3366
Site inspections
5

Schedule

Between October 2025 and September 2026 the site added about 1.3 points a month. At that rate it would finish around September 2031, more than three months after its registered date of June 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 September 2026

20%+2.9 pts

  • One Park Square By Iman construction site, inspection photo 1, 22 September 2026
  • One Park Square By Iman construction site, inspection photo 2, 22 September 2026
  • One Park Square By Iman construction site, inspection photo 3, 22 September 2026
  • One Park Square By Iman construction site, inspection photo 4, 22 September 2026

6 August 2026

17%+11 pts

  • One Park Square By Iman construction site, inspection photo 1, 6 August 2026
  • One Park Square By Iman construction site, inspection photo 2, 6 August 2026
  • One Park Square By Iman construction site, inspection photo 3, 6 August 2026
  • One Park Square By Iman construction site, inspection photo 4, 6 August 2026

14 January 2026

6.4%+1.7 pts

  • One Park Square By Iman construction site, inspection photo 1, 14 January 2026
  • One Park Square By Iman construction site, inspection photo 2, 14 January 2026
  • One Park Square By Iman construction site, inspection photo 3, 14 January 2026

7 October 2025

4.7%+4.7 pts

  • One Park Square By Iman construction site, inspection photo 1, 7 October 2025
  • One Park Square By Iman construction site, inspection photo 2, 7 October 2025
  • One Park Square By Iman construction site, inspection photo 3, 7 October 2025
  • One Park Square By Iman construction site, inspection photo 4, 7 October 2025

12 November 2024

0%

  • One Park Square By Iman construction site, inspection photo 1, 12 November 2024
  • One Park Square By Iman construction site, inspection photo 2, 12 November 2024

All 20 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Iman Developers has 10 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in One Park Square By Iman?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the One Park Square By Iman handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on One Park Square By Iman?
One Park Square By Iman was 20% built at the site inspection on 22 September 2026. The site has been inspected 5 times since November 2024. The Land Department took 20 site photos at its inspections.
Is One Park Square By Iman delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building One Park Square By Iman?
The registered developer is Iman Developers. It has 9 other projects under construction in Dubai.
Which bank holds the escrow account for One Park Square By Iman?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.