One Park Central By Iman construction photos
34 photos from 6 site inspections, newest first. The percentage is how much of One Park Central By Iman was built on the day of each visit.
28 October 202632% built
11 March 202620% built
24 December 202512% built
27 May 20256.1% built
23 December 20243.0% built
1 March 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.