Maison Elysee Iii By Pantheon construction progress

Maison Elysee Iii By Pantheon in Jumeirah Village Circle is 4.4% built at the Land Department inspection of June 2026. Developer Pantheon Elysee Real Estate Development. Completion registered for October 2027.

4.4%

Built, at the Land Department site inspection of 25 June 2026

Running behind its date

Completion date (Land Department)
October 2027
Finish at recent pace
November 2054
Construction started
November 2024
Registered with the Land Department
January 2025
Units
379
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
مزون اليزيه Iii من بانثيون
Land Department project number
3281
Land Department site inspections
5

Schedule

Between November 2025 and June 2026 the site added about 0.3 points a month. At that rate it would finish around November 2054, more than three months after the October 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 June 2026

4.4%+0.8 pts

  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 1, 25 June 2026
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 2, 25 June 2026
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 3, 25 June 2026
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 4, 25 June 2026

31 March 2026

3.6%+1.3 pts

  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 1, 31 March 2026
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 2, 31 March 2026
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 3, 31 March 2026
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 4, 31 March 2026

10 November 2025

2.3%+2.1 pts

  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 1, 10 November 2025
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 2, 10 November 2025
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 3, 10 November 2025
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 4, 10 November 2025

13 May 2025

0.2%+0.2 pts

  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 1, 13 May 2025
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 2, 13 May 2025
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 3, 13 May 2025
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 4, 13 May 2025

11 October 2024

0%

  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 1, 11 October 2024
  • Maison Elysee Iii By Pantheon construction site, Land Department inspection photo 2, 11 October 2024

All 21 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Pantheon Elysee Real Estate Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Maison Elysee Iii By Pantheon?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Maison Elysee Iii By Pantheon be completed?
The completion date registered with the Dubai Land Department is October 2027. At the pace of its recent inspections the site would reach 100% around November 2054. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Maison Elysee Iii By Pantheon is built?
4.4%, measured at the Land Department site inspection on 25 June 2026. The Land Department engineers have inspected the site 5 times since October 2024.
Is Maison Elysee Iii By Pantheon delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Maison Elysee Iii By Pantheon?
The registered developer is Pantheon Elysee Real Estate Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Maison Elysee Iii By Pantheon?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.