Maison Elysee III By Pantheon construction progress

The registered completion date for Maison Elysee III By Pantheon in Jumeirah Village Circle is October 2027. At the last site inspection, in November 2026, it was 6.0% built. The developer is Pantheon Elysee Real Estate Development.

6.0%

Built, at the site inspection of 18 November 2026

Running behind its date

Registered completion date
October 2027
Finish at recent pace
June 2051
Construction started
November 2024
First registered
January 2025
Units
379
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
مزون اليزيه Iii من بانثيون
Project number
3281
Site inspections
6

Schedule

Between March 2026 and November 2026 the site added about 0.3 points a month. At that rate it would finish around June 2051, more than three months after its registered date of October 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 November 2026

6.0%+1.6 pts

  • Maison Elysee III By Pantheon construction site, inspection photo 1, 18 November 2026
  • Maison Elysee III By Pantheon construction site, inspection photo 2, 18 November 2026
  • Maison Elysee III By Pantheon construction site, inspection photo 3, 18 November 2026
  • Maison Elysee III By Pantheon construction site, inspection photo 4, 18 November 2026

25 June 2026

4.4%+0.8 pts

  • Maison Elysee III By Pantheon construction site, inspection photo 1, 25 June 2026
  • Maison Elysee III By Pantheon construction site, inspection photo 2, 25 June 2026
  • Maison Elysee III By Pantheon construction site, inspection photo 3, 25 June 2026
  • Maison Elysee III By Pantheon construction site, inspection photo 4, 25 June 2026

31 March 2026

3.6%+1.3 pts

  • Maison Elysee III By Pantheon construction site, inspection photo 1, 31 March 2026
  • Maison Elysee III By Pantheon construction site, inspection photo 2, 31 March 2026
  • Maison Elysee III By Pantheon construction site, inspection photo 3, 31 March 2026
  • Maison Elysee III By Pantheon construction site, inspection photo 4, 31 March 2026

10 November 2025

2.3%+2.1 pts

  • Maison Elysee III By Pantheon construction site, inspection photo 1, 10 November 2025
  • Maison Elysee III By Pantheon construction site, inspection photo 2, 10 November 2025
  • Maison Elysee III By Pantheon construction site, inspection photo 3, 10 November 2025
  • Maison Elysee III By Pantheon construction site, inspection photo 4, 10 November 2025

13 May 2025

0.2%+0.2 pts

  • Maison Elysee III By Pantheon construction site, inspection photo 1, 13 May 2025
  • Maison Elysee III By Pantheon construction site, inspection photo 2, 13 May 2025
  • Maison Elysee III By Pantheon construction site, inspection photo 3, 13 May 2025
  • Maison Elysee III By Pantheon construction site, inspection photo 4, 13 May 2025

11 October 2024

0%

  • Maison Elysee III By Pantheon construction site, inspection photo 1, 11 October 2024
  • Maison Elysee III By Pantheon construction site, inspection photo 2, 11 October 2024

All 25 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Pantheon Elysee Real Estate Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Maison Elysee III By Pantheon?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Maison Elysee III By Pantheon handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2051. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Maison Elysee III By Pantheon?
Maison Elysee III By Pantheon was 6.0% built at the site inspection on 18 November 2026. The site has been inspected 6 times since October 2024. The Land Department took 25 site photos at its inspections.
Is Maison Elysee III By Pantheon delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Maison Elysee III By Pantheon?
The registered developer is Pantheon Elysee Real Estate Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Maison Elysee III By Pantheon?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.