Elysee Heights construction progress

Elysee Heights in Jumeirah Village Circle is 81% built at the Land Department inspection of June 2026. Developer Pantheon Elysee Real Estate Development. Completion registered for April 2026.

81%

Built, at the Land Department site inspection of 1 June 2026

6 months past its registered completion date

Completion date (Land Department)
April 2026
Finish at recent pace
September 2026
Construction started
April 2023
Registered with the Land Department
July 2023
Units
193
Escrow bank
Emirates NBD
Name in Arabic
اليسي هايتس
Land Department project number
2660
Land Department site inspections
6

Schedule

Elysee Heights was registered to complete in April 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 4.7 points a month. Kept at that rate, the site would reach 100% around September 2026.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 June 2026

81%+24 pts

  • Elysee Heights construction site, Land Department inspection photo 1, 1 June 2026
  • Elysee Heights construction site, Land Department inspection photo 2, 1 June 2026
  • Elysee Heights construction site, Land Department inspection photo 3, 1 June 2026
  • Elysee Heights construction site, Land Department inspection photo 4, 1 June 2026

4 February 2026

58%+10 pts

  • Elysee Heights construction site, Land Department inspection photo 1, 4 February 2026
  • Elysee Heights construction site, Land Department inspection photo 2, 4 February 2026
  • Elysee Heights construction site, Land Department inspection photo 3, 4 February 2026
  • Elysee Heights construction site, Land Department inspection photo 4, 4 February 2026

24 October 2025

47%+15 pts

  • Elysee Heights construction site, Land Department inspection photo 1, 24 October 2025
  • Elysee Heights construction site, Land Department inspection photo 2, 24 October 2025
  • Elysee Heights construction site, Land Department inspection photo 3, 24 October 2025
  • Elysee Heights construction site, Land Department inspection photo 4, 24 October 2025

6 May 2025

32%+32 pts

  • Elysee Heights construction site, Land Department inspection photo 1, 6 May 2025
  • Elysee Heights construction site, Land Department inspection photo 2, 6 May 2025
  • Elysee Heights construction site, Land Department inspection photo 3, 6 May 2025
  • Elysee Heights construction site, Land Department inspection photo 4, 6 May 2025

20 November 2023

0%+0.0 pts

  • Elysee Heights construction site, Land Department inspection photo 1, 20 November 2023
  • Elysee Heights construction site, Land Department inspection photo 2, 20 November 2023
  • Elysee Heights construction site, Land Department inspection photo 3, 20 November 2023

22 May 2023

0%

  • Elysee Heights construction site, Land Department inspection photo 1, 22 May 2023
  • Elysee Heights construction site, Land Department inspection photo 2, 22 May 2023
  • Elysee Heights construction site, Land Department inspection photo 3, 22 May 2023

All 44 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Pantheon Elysee Real Estate Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Elysee Heights?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Elysee Heights be completed?
The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Elysee Heights is built?
81%, measured at the Land Department site inspection on 1 June 2026. The Land Department engineers have inspected the site 6 times since May 2023.
Is Elysee Heights delayed?
Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
Who is building Elysee Heights?
The registered developer is Pantheon Elysee Real Estate Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Elysee Heights?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.