Elysee Heights construction progress

Elysee Heights in Jumeirah Village Circle was registered to complete in April 2026 and is still under construction. At the last site inspection, in November 2026, it was 97% built. The developer is Pantheon Elysee Real Estate Development.

97%

Built, at the site inspection of 23 November 2026

7 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
December 2026
Construction started
April 2023
First registered
July 2023
Units
193
Escrow bank
Emirates NBD
Name in Arabic
اليسي هايتس
Project number
2660
Site inspections
7

Schedule

Elysee Heights was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 4.1 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 November 2026

97%+16 pts

  • Elysee Heights construction site, inspection photo 1, 23 November 2026
  • Elysee Heights construction site, inspection photo 2, 23 November 2026
  • Elysee Heights construction site, inspection photo 3, 23 November 2026
  • Elysee Heights construction site, inspection photo 4, 23 November 2026

1 June 2026

81%+24 pts

  • Elysee Heights construction site, inspection photo 1, 1 June 2026
  • Elysee Heights construction site, inspection photo 2, 1 June 2026
  • Elysee Heights construction site, inspection photo 3, 1 June 2026
  • Elysee Heights construction site, inspection photo 4, 1 June 2026

4 February 2026

58%+10 pts

  • Elysee Heights construction site, inspection photo 1, 4 February 2026
  • Elysee Heights construction site, inspection photo 2, 4 February 2026
  • Elysee Heights construction site, inspection photo 3, 4 February 2026
  • Elysee Heights construction site, inspection photo 4, 4 February 2026

24 October 2025

47%+15 pts

  • Elysee Heights construction site, inspection photo 1, 24 October 2025
  • Elysee Heights construction site, inspection photo 2, 24 October 2025
  • Elysee Heights construction site, inspection photo 3, 24 October 2025
  • Elysee Heights construction site, inspection photo 4, 24 October 2025

6 May 2025

32%+32 pts

  • Elysee Heights construction site, inspection photo 1, 6 May 2025
  • Elysee Heights construction site, inspection photo 2, 6 May 2025
  • Elysee Heights construction site, inspection photo 3, 6 May 2025
  • Elysee Heights construction site, inspection photo 4, 6 May 2025

20 November 2023

0%+0.0 pts

  • Elysee Heights construction site, inspection photo 1, 20 November 2023
  • Elysee Heights construction site, inspection photo 2, 20 November 2023
  • Elysee Heights construction site, inspection photo 3, 20 November 2023

22 May 2023

0%

  • Elysee Heights construction site, inspection photo 1, 22 May 2023
  • Elysee Heights construction site, inspection photo 2, 22 May 2023
  • Elysee Heights construction site, inspection photo 3, 22 May 2023

All 54 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Pantheon Elysee Real Estate Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Elysee Heights?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Elysee Heights handover date?
The registered completion date was April 2026, and the register still lists Elysee Heights as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Elysee Heights?
Elysee Heights was 97% built at the site inspection on 23 November 2026. The site has been inspected 7 times since May 2023. The Land Department took 54 site photos at its inspections.
Is Elysee Heights delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Elysee Heights?
The registered developer is Pantheon Elysee Real Estate Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Elysee Heights?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.