Elysee Heights construction progress
Elysee Heights in Jumeirah Village Circle is 81% built at the Land Department inspection of June 2026. Developer Pantheon Elysee Real Estate Development. Completion registered for April 2026.
81%
Built, at the Land Department site inspection of 1 June 2026
6 months past its registered completion date
- Completion date (Land Department)
- April 2026
- Finish at recent pace
- September 2026
- Construction started
- April 2023
- Registered with the Land Department
- July 2023
- Community
- Jumeirah Village Circle
- Units
- 193
- Escrow bank
- Emirates NBD
- Name in Arabic
- اليسي هايتس
- Land Department project number
- 2660
- Land Department site inspections
- 6
Schedule
Elysee Heights was registered to complete in April 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 4.7 points a month. Kept at that rate, the site would reach 100% around September 2026.
Site inspections
1 June 2026
81%+24 pts
4 February 2026
58%+10 pts
24 October 2025
47%+15 pts
6 May 2025
32%+32 pts
20 November 2023
0%+0.0 pts
22 May 2023
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Pantheon Elysee Real Estate Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Elysee Heights?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Elysee Heights be completed?
- The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Elysee Heights is built?
- 81%, measured at the Land Department site inspection on 1 June 2026. The Land Department engineers have inspected the site 6 times since May 2023.
- Is Elysee Heights delayed?
- Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
- Who is building Elysee Heights?
- The registered developer is Pantheon Elysee Real Estate Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Elysee Heights?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Maison Elysee IiAlso by Pantheon Elysee Real Estate Development. 23%.
- Maison Elysee IAlso by Pantheon Elysee Real Estate Development. 21%.
- Maison Elysee Iii By PantheonAlso by Pantheon Elysee Real Estate Development. 4.4%, Due October 2027.
- Voxa ResidencesAlso by Pantheon Elysee Real Estate Development. 4.5%, Due December 2028.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)