Skip to content

Voxa Residences construction progress

Voxa Residences in Jumeirah Village Triangle is 4.5% built at the Land Department inspection of June 2026. Developer Pantheon Elysee Real Estate Development. Completion registered for December 2028.

4.5%

Built, at the Land Department site inspection of 1 June 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
April 2034
Construction started
July 2025
Registered with the Land Department
July 2025
Units
599
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
Voxa Residences
Land Department project number
3736
Land Department site inspections
3

Schedule

Between February 2026 and June 2026 the site added about 1.0 points a month. At that rate it would finish around April 2034, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 June 2026

4.5%+3.7 pts

  • Voxa Residences construction site, Land Department inspection photo 1, 1 June 2026
  • Voxa Residences construction site, Land Department inspection photo 2, 1 June 2026
  • Voxa Residences construction site, Land Department inspection photo 3, 1 June 2026
  • Voxa Residences construction site, Land Department inspection photo 4, 1 June 2026

11 February 2026

0.8%+0.8 pts

  • Voxa Residences construction site, Land Department inspection photo 1, 11 February 2026
  • Voxa Residences construction site, Land Department inspection photo 2, 11 February 2026
  • Voxa Residences construction site, Land Department inspection photo 3, 11 February 2026

14 May 2025

0%

  • Voxa Residences construction site, Land Department inspection photo 1, 14 May 2025
  • Voxa Residences construction site, Land Department inspection photo 2, 14 May 2025

All 10 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average. Voxa Residences is behind that average.

Pantheon Elysee Real Estate Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Voxa Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Voxa Residences be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around April 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Voxa Residences is built?
4.5%, measured at the Land Department site inspection on 1 June 2026. The Land Department engineers have inspected the site 3 times since May 2025.
Is Voxa Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Voxa Residences?
The registered developer is Pantheon Elysee Real Estate Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Voxa Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.