Skip to content

Maison Elysee I construction progress

The registered completion date for Maison Elysee I in Jumeirah Village Circle is March 2027. At the last site inspection, in July 2026, it was 21% built. The developer is Pantheon Elysee Real Estate Development.

21%

Built, at the site inspection of 6 July 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
August 2030
Construction started
April 2024
First registered
February 2024
Units
355
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
( مايسون الاليزيه I )
Project number
2905
Site inspections
5

Schedule

Between December 2025 and July 2026 the site added about 1.6 points a month. At that rate it would finish around August 2030, more than three months after its registered date of March 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 July 2026

21%+4.3 pts

  • Maison Elysee I construction site, inspection photo 1, 6 July 2026
  • Maison Elysee I construction site, inspection photo 2, 6 July 2026
  • Maison Elysee I construction site, inspection photo 3, 6 July 2026
  • Maison Elysee I construction site, inspection photo 4, 6 July 2026

30 March 2026

17%+7.0 pts

  • Maison Elysee I construction site, inspection photo 1, 30 March 2026
  • Maison Elysee I construction site, inspection photo 2, 30 March 2026
  • Maison Elysee I construction site, inspection photo 3, 30 March 2026
  • Maison Elysee I construction site, inspection photo 4, 30 March 2026

3 December 2025

9.8%+7.0 pts

  • Maison Elysee I construction site, inspection photo 1, 3 December 2025
  • Maison Elysee I construction site, inspection photo 2, 3 December 2025
  • Maison Elysee I construction site, inspection photo 3, 3 December 2025
  • Maison Elysee I construction site, inspection photo 4, 3 December 2025

30 June 2025

2.8%+2.8 pts

  • Maison Elysee I construction site, inspection photo 1, 30 June 2025
  • Maison Elysee I construction site, inspection photo 2, 30 June 2025
  • Maison Elysee I construction site, inspection photo 3, 30 June 2025

16 January 2024

0%

  • Maison Elysee I construction site, inspection photo 1, 16 January 2024
  • Maison Elysee I construction site, inspection photo 2, 16 January 2024
  • Maison Elysee I construction site, inspection photo 3, 16 January 2024

All 27 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Pantheon Elysee Real Estate Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Maison Elysee I?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Maison Elysee I handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Maison Elysee I?
Maison Elysee I was 21% built at the site inspection on 6 July 2026. The site has been inspected 5 times since January 2024. The Land Department took 27 site photos at its inspections.
Is Maison Elysee I delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Maison Elysee I?
The registered developer is Pantheon Elysee Real Estate Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Maison Elysee I?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.