Maison Elysee I construction progress
The registered completion date for Maison Elysee I in Jumeirah Village Circle is March 2027. At the last site inspection, in July 2026, it was 21% built. The developer is Pantheon Elysee Real Estate Development.
21%
Built, at the site inspection of 6 July 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- August 2030
- Construction started
- April 2024
- First registered
- February 2024
- Community
- Jumeirah Village Circle
- Units
- 355
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ( مايسون الاليزيه I )
- Project number
- 2905
- Site inspections
- 5
Schedule
Between December 2025 and July 2026 the site added about 1.6 points a month. At that rate it would finish around August 2030, more than three months after its registered date of March 2027.
Site inspections
6 July 2026
21%+4.3 pts
30 March 2026
17%+7.0 pts
3 December 2025
9.8%+7.0 pts
30 June 2025
2.8%+2.8 pts
16 January 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Pantheon Elysee Real Estate Development has 6 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Maison Elysee I?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Maison Elysee I handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Maison Elysee I?
- Maison Elysee I was 21% built at the site inspection on 6 July 2026. The site has been inspected 5 times since January 2024. The Land Department took 27 site photos at its inspections.
- Is Maison Elysee I delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Maison Elysee I?
- The registered developer is Pantheon Elysee Real Estate Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Maison Elysee I?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elysee HeightsAlso by Pantheon Elysee Real Estate Development. 97%, Due April 2026, passed.
- Maison Elysee IIAlso by Pantheon Elysee Real Estate Development. 23%.
- Maison Elysee III By PantheonAlso by Pantheon Elysee Real Estate Development. 6.0%, Due October 2027.
- Voxa ResidencesAlso by Pantheon Elysee Real Estate Development. 4.5%, Due December 2028.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.