Belgravia III construction progress

The register lists Belgravia III in Jumeirah Village Circle as complete, with a registered completion date of December 2021. Its last site inspection on record was in December 2021. The developer is Ellington Properties Development.

100%

Built, at the site inspection of 29 December 2021

Construction complete

Registered completion date
December 2021
Construction started
June 2017
First registered
July 2017
Units
260
Escrow bank
Commercial Bank International
Name in Arabic
Iii بلغرافيا
Project number
1922
Site inspections
11

Schedule

The register lists Belgravia III as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 December 2021

100%+20 pts

  • Belgravia III construction site, inspection photo 1, 29 December 2021
  • Belgravia III construction site, inspection photo 2, 29 December 2021
  • Belgravia III construction site, inspection photo 3, 29 December 2021
  • Belgravia III construction site, inspection photo 4, 29 December 2021

24 June 2021

80%+14 pts

  • Belgravia III construction site, inspection photo 1, 24 June 2021
  • Belgravia III construction site, inspection photo 2, 24 June 2021
  • Belgravia III construction site, inspection photo 3, 24 June 2021
  • Belgravia III construction site, inspection photo 4, 24 June 2021

8 March 2021

66%+6.2 pts

  • Belgravia III construction site, inspection photo 1, 8 March 2021
  • Belgravia III construction site, inspection photo 2, 8 March 2021
  • Belgravia III construction site, inspection photo 3, 8 March 2021
  • Belgravia III construction site, inspection photo 4, 8 March 2021

21 January 2021

60%+9.9 pts

  • Belgravia III construction site, inspection photo 1, 21 January 2021
  • Belgravia III construction site, inspection photo 2, 21 January 2021
  • Belgravia III construction site, inspection photo 3, 21 January 2021
  • Belgravia III construction site, inspection photo 4, 21 January 2021

18 October 2020

50%+16 pts

  • Belgravia III construction site, inspection photo 1, 18 October 2020
  • Belgravia III construction site, inspection photo 2, 18 October 2020
  • Belgravia III construction site, inspection photo 3, 18 October 2020
  • Belgravia III construction site, inspection photo 4, 18 October 2020

4 May 2020

34%+0.5 pts

  • Belgravia III construction site, inspection photo 1, 4 May 2020
  • Belgravia III construction site, inspection photo 2, 4 May 2020
  • Belgravia III construction site, inspection photo 3, 4 May 2020
  • Belgravia III construction site, inspection photo 4, 4 May 2020

19 May 2019

34%+3.6 pts

  • Belgravia III construction site, inspection photo 1, 19 May 2019
  • Belgravia III construction site, inspection photo 2, 19 May 2019
  • Belgravia III construction site, inspection photo 3, 19 May 2019
  • Belgravia III construction site, inspection photo 4, 19 May 2019

18 December 2018

30%+9.3 pts

  • Belgravia III construction site, inspection photo 1, 18 December 2018
  • Belgravia III construction site, inspection photo 2, 18 December 2018
  • Belgravia III construction site, inspection photo 3, 18 December 2018
  • Belgravia III construction site, inspection photo 4, 18 December 2018

2 August 2018

21%+11 pts

  • Belgravia III construction site, inspection photo 1, 2 August 2018
  • Belgravia III construction site, inspection photo 2, 2 August 2018
  • Belgravia III construction site, inspection photo 3, 2 August 2018
  • Belgravia III construction site, inspection photo 4, 2 August 2018

12 March 2018

10%+4.2 pts

  • Belgravia III construction site, inspection photo 1, 12 March 2018
  • Belgravia III construction site, inspection photo 2, 12 March 2018
  • Belgravia III construction site, inspection photo 3, 12 March 2018
  • Belgravia III construction site, inspection photo 4, 12 March 2018

All 102 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Belgravia III?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Belgravia III handover date?
Construction of Belgravia III is recorded as complete, with a registered completion date of December 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Belgravia III?
Belgravia III was 100% built at the site inspection on 29 December 2021. The site has been inspected 11 times since November 2017. The Land Department took 102 site photos at its inspections.
Is Belgravia III delayed?
The register lists construction as complete.
Who is building Belgravia III?
The registered developer is Ellington Properties Development. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Belgravia III?
Commercial Bank International. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.