Belgravia III construction photos

102 photos from 11 site inspections, newest first. The percentage is how much of Belgravia III was built on the day of each visit.

29 December 2021100% built

24 June 202180% built

8 March 202166% built

21 January 202160% built

18 October 202050% built

4 May 202034% built

19 May 201934% built

18 December 201830% built

2 August 201821% built

12 March 201810% built

9 November 20176.2% built

Back to Belgravia III construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.