Aveline Residences By Citi Developers construction progress
Aveline Residences By Citi Developers in Jumeirah Village Circle is 42% built at the Land Department inspection of June 2026. Developer Citi Developers Real Estate Development. Completion registered for July 2026.
42%
Built, at the Land Department site inspection of 25 June 2026
3 months past its registered completion date
- Completion date (Land Department)
- July 2026
- Finish at recent pace
- February 2028
- Construction started
- February 2024
- Registered with the Land Department
- January 2024
- Community
- Jumeirah Village Circle
- Units
- 265
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- افيلين ريزيدنسز من سيتي ديفيلوبرز
- Land Department project number
- 2864
- Land Department site inspections
- 7
Schedule
Aveline Residences By Citi Developers was registered to complete in July 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 3.0 points a month. Kept at that rate, the site would reach 100% around February 2028.
Site inspections
25 June 2026
42%+12 pts
24 February 2026
30%+9.7 pts
12 November 2025
20%+6.4 pts
19 June 2025
14%+4.3 pts
14 February 2025
9.7%+4.1 pts
13 November 2024
5.5%+5.5 pts
5 December 2023
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Citi Developers Real Estate Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Aveline Residences By Citi Developers?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Aveline Residences By Citi Developers be completed?
- The completion date registered with the Dubai Land Department is July 2026. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Aveline Residences By Citi Developers is built?
- 42%, measured at the Land Department site inspection on 25 June 2026. The Land Department engineers have inspected the site 7 times since December 2023.
- Is Aveline Residences By Citi Developers delayed?
- Yes. Its registered completion date of July 2026 has passed and the Land Department still lists it as under construction.
- Who is building Aveline Residences By Citi Developers?
- The registered developer is Citi Developers Real Estate Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Aveline Residences By Citi Developers?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Allura Residences By Citi DevelopersAlso by Citi Developers Real Estate Development. 7.8%, Due July 2027.
- Agua Residences By Citi Developers - Tower 2Also by Citi Developers Real Estate Development. 3.1%, Due December 2027.
- Agua Residences By Citi Developers - Tower 1Also by Citi Developers Real Estate Development. 5.0%, Due December 2027.
- Arya Residences By Citi DevelopersAlso by Citi Developers Real Estate Development. 3.0%, Due December 2027.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.











.jpeg&w=3840&q=75)