Agua Residences By Citi Developers - Tower 1 construction progress

Agua Residences By Citi Developers - Tower 1 in Palm Deira is 5.0% built at the Land Department inspection of June 2026. Developer Citi Developers Real Estate Development. Completion registered for December 2027.

5.0%

Built, at the Land Department site inspection of 22 June 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
July 2044
Construction started
August 2025
Registered with the Land Department
August 2025
Community
Palm Deira
Units
61
Escrow bank
The National Bank of Fujairah
Name in Arabic
أغوا ريزيدنسز من سيتي ديفيلوبرز - تاور 1
Land Department project number
3872
Land Department site inspections
3

Schedule

Between July 2025 and June 2026 the site added about 0.4 points a month. At that rate it would finish around July 2044, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 June 2026

5.0%+5.0 pts

  • Agua Residences By Citi Developers - Tower 1 construction site, Land Department inspection photo 1, 22 June 2026
  • Agua Residences By Citi Developers - Tower 1 construction site, Land Department inspection photo 2, 22 June 2026
  • Agua Residences By Citi Developers - Tower 1 construction site, Land Department inspection photo 3, 22 June 2026
  • Agua Residences By Citi Developers - Tower 1 construction site, Land Department inspection photo 4, 22 June 2026

16 February 2026

0%+0.0 pts

  • Agua Residences By Citi Developers - Tower 1 construction site, Land Department inspection photo 1, 16 February 2026
  • Agua Residences By Citi Developers - Tower 1 construction site, Land Department inspection photo 2, 16 February 2026

9 July 2025

0%

  • Agua Residences By Citi Developers - Tower 1 construction site, Land Department inspection photo 1, 9 July 2025
  • Agua Residences By Citi Developers - Tower 1 construction site, Land Department inspection photo 2, 9 July 2025

All 9 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Citi Developers Real Estate Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Agua Residences By Citi Developers - Tower 1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Agua Residences By Citi Developers - Tower 1 be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around July 2044. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Agua Residences By Citi Developers - Tower 1 is built?
5.0%, measured at the Land Department site inspection on 22 June 2026. The Land Department engineers have inspected the site 3 times since July 2025.
Is Agua Residences By Citi Developers - Tower 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Agua Residences By Citi Developers - Tower 1?
The registered developer is Citi Developers Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Agua Residences By Citi Developers - Tower 1?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.