Aveline Residences By Citi Developers construction photos
39 photos from 7 site inspections, newest first. The percentage is how much of Aveline Residences By Citi Developers was built on the day of each visit.
25 June 202642% built
24 February 202630% built
12 November 202520% built
19 June 202514% built
14 February 20259.7% built
13 November 20245.5% built
5 December 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.