Allura Residences By Citi Developers construction progress
The registered completion date for Allura Residences By Citi Developers in Jumeirah Village Circle is July 2027. At the last site inspection, in June 2026, it was 7.8% built. The developer is Citi Developers Real Estate Development.
7.8%
Built, at the site inspection of 23 June 2026
Running behind its date
- Registered completion date
- July 2027
- Finish at recent pace
- December 2033
- Construction started
- December 2024
- First registered
- February 2025
- Community
- Jumeirah Village Circle
- Units
- 264
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- ألورا ريزيدنس من سيتي ديفيلوبرز
- Project number
- 3289
- Site inspections
- 4
Schedule
Between November 2025 and June 2026 the site added about 1.0 points a month. At that rate it would finish around December 2033, more than three months after its registered date of July 2027.
Site inspections
23 June 2026
7.8%+3.5 pts
26 February 2026
4.2%+3.8 pts
19 November 2025
0.5%+0.5 pts
3 October 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Citi Developers Real Estate Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Allura Residences By Citi Developers?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Allura Residences By Citi Developers handover date?
- The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Allura Residences By Citi Developers?
- Allura Residences By Citi Developers was 7.8% built at the site inspection on 23 June 2026. The site has been inspected 4 times since October 2024. The Land Department took 15 site photos at its inspections.
- Is Allura Residences By Citi Developers delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
- Who is building Allura Residences By Citi Developers?
- The registered developer is Citi Developers Real Estate Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Allura Residences By Citi Developers?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Aveline Residences By Citi DevelopersAlso by Citi Developers Real Estate Development. 42%, Due July 2026, passed.
- Agua Residences By Citi Developers - Tower 2Also by Citi Developers Real Estate Development. 3.1%, Due December 2027.
- Agua Residences By Citi Developers - Tower 1Also by Citi Developers Real Estate Development. 5.0%, Due December 2027.
- Arya Residences By Citi DevelopersAlso by Citi Developers Real Estate Development. 3.0%, Due December 2027.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)