Allura Residences By Citi Developers construction progress

The registered completion date for Allura Residences By Citi Developers in Jumeirah Village Circle is July 2027. At the last site inspection, in June 2026, it was 7.8% built. The developer is Citi Developers Real Estate Development.

7.8%

Built, at the site inspection of 23 June 2026

Running behind its date

Registered completion date
July 2027
Finish at recent pace
December 2033
Construction started
December 2024
First registered
February 2025
Units
264
Escrow bank
The National Bank of Fujairah
Name in Arabic
ألورا ريزيدنس من سيتي ديفيلوبرز
Project number
3289
Site inspections
4

Schedule

Between November 2025 and June 2026 the site added about 1.0 points a month. At that rate it would finish around December 2033, more than three months after its registered date of July 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 June 2026

7.8%+3.5 pts

  • Allura Residences By Citi Developers construction site, inspection photo 1, 23 June 2026
  • Allura Residences By Citi Developers construction site, inspection photo 2, 23 June 2026
  • Allura Residences By Citi Developers construction site, inspection photo 3, 23 June 2026
  • Allura Residences By Citi Developers construction site, inspection photo 4, 23 June 2026

26 February 2026

4.2%+3.8 pts

  • Allura Residences By Citi Developers construction site, inspection photo 1, 26 February 2026
  • Allura Residences By Citi Developers construction site, inspection photo 2, 26 February 2026
  • Allura Residences By Citi Developers construction site, inspection photo 3, 26 February 2026
  • Allura Residences By Citi Developers construction site, inspection photo 4, 26 February 2026

19 November 2025

0.5%+0.5 pts

  • Allura Residences By Citi Developers construction site, inspection photo 1, 19 November 2025
  • Allura Residences By Citi Developers construction site, inspection photo 2, 19 November 2025
  • Allura Residences By Citi Developers construction site, inspection photo 3, 19 November 2025

3 October 2024

0%

  • Allura Residences By Citi Developers construction site, inspection photo 1, 3 October 2024
  • Allura Residences By Citi Developers construction site, inspection photo 2, 3 October 2024

All 15 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Citi Developers Real Estate Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Allura Residences By Citi Developers?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Allura Residences By Citi Developers handover date?
The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Allura Residences By Citi Developers?
Allura Residences By Citi Developers was 7.8% built at the site inspection on 23 June 2026. The site has been inspected 4 times since October 2024. The Land Department took 15 site photos at its inspections.
Is Allura Residences By Citi Developers delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Allura Residences By Citi Developers?
The registered developer is Citi Developers Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Allura Residences By Citi Developers?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.