Allura Residences By Citi Developers construction progress

Allura Residences By Citi Developers in Jumeirah Village Circle is 7.8% built at the Land Department inspection of June 2026. Developer Citi Developers Real Estate Development. Completion registered for July 2027.

7.8%

Built, at the Land Department site inspection of 23 June 2026

Running behind its date

Completion date (Land Department)
July 2027
Finish at recent pace
December 2033
Construction started
December 2024
Registered with the Land Department
February 2025
Units
264
Escrow bank
The National Bank of Fujairah
Name in Arabic
ألورا ريزيدنس من سيتي ديفيلوبرز
Land Department project number
3289
Land Department site inspections
4

Schedule

Between November 2025 and June 2026 the site added about 1.0 points a month. At that rate it would finish around December 2033, more than three months after the July 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 June 2026

7.8%+3.5 pts

  • Allura Residences By Citi Developers construction site, Land Department inspection photo 1, 23 June 2026
  • Allura Residences By Citi Developers construction site, Land Department inspection photo 2, 23 June 2026
  • Allura Residences By Citi Developers construction site, Land Department inspection photo 3, 23 June 2026
  • Allura Residences By Citi Developers construction site, Land Department inspection photo 4, 23 June 2026

26 February 2026

4.2%+3.8 pts

  • Allura Residences By Citi Developers construction site, Land Department inspection photo 1, 26 February 2026
  • Allura Residences By Citi Developers construction site, Land Department inspection photo 2, 26 February 2026
  • Allura Residences By Citi Developers construction site, Land Department inspection photo 3, 26 February 2026
  • Allura Residences By Citi Developers construction site, Land Department inspection photo 4, 26 February 2026

19 November 2025

0.5%+0.5 pts

  • Allura Residences By Citi Developers construction site, Land Department inspection photo 1, 19 November 2025
  • Allura Residences By Citi Developers construction site, Land Department inspection photo 2, 19 November 2025
  • Allura Residences By Citi Developers construction site, Land Department inspection photo 3, 19 November 2025

3 October 2024

0%

  • Allura Residences By Citi Developers construction site, Land Department inspection photo 1, 3 October 2024
  • Allura Residences By Citi Developers construction site, Land Department inspection photo 2, 3 October 2024

All 15 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Citi Developers Real Estate Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Allura Residences By Citi Developers?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Allura Residences By Citi Developers be completed?
The completion date registered with the Dubai Land Department is July 2027. At the pace of its recent inspections the site would reach 100% around December 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Allura Residences By Citi Developers is built?
7.8%, measured at the Land Department site inspection on 23 June 2026. The Land Department engineers have inspected the site 4 times since October 2024.
Is Allura Residences By Citi Developers delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Allura Residences By Citi Developers?
The registered developer is Citi Developers Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Allura Residences By Citi Developers?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.