Agua Residences By Citi Developers - Tower 2 construction progress
The registered completion date for Agua Residences By Citi Developers - Tower 2 in Palm Deira is December 2027. At the last site inspection, in September 2026, it was 3.1% built. The developer is Citi Developers Real Estate Development.
3.1%
Built, at the site inspection of 15 September 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- November 2047
- Construction started
- August 2025
- First registered
- June 2025
- Community
- Palm Deira
- Units
- 61
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- أغوا ريزيدنسز من سيتي ديفيلوبرز - تاور 2
- Project number
- 3756
- Site inspections
- 4
Schedule
Between January 2026 and September 2026 the site added about 0.4 points a month. At that rate it would finish around November 2047, more than three months after its registered date of December 2027.
Site inspections
15 September 2026
3.1%+0.7 pts
29 April 2026
2.5%+2.4 pts
13 January 2026
0%+0.0 pts
3 June 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Citi Developers Real Estate Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Agua Residences By Citi Developers - Tower 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Agua Residences By Citi Developers - Tower 2 handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2047. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Agua Residences By Citi Developers - Tower 2?
- Agua Residences By Citi Developers - Tower 2 was 3.1% built at the site inspection on 15 September 2026. The site has been inspected 4 times since June 2025. The Land Department took 15 site photos at its inspections.
- Is Agua Residences By Citi Developers - Tower 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Agua Residences By Citi Developers - Tower 2?
- The registered developer is Citi Developers Real Estate Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Agua Residences By Citi Developers - Tower 2?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Aveline Residences By Citi DevelopersAlso by Citi Developers Real Estate Development. 42%, Due July 2026, passed.
- Allura Residences By Citi DevelopersAlso by Citi Developers Real Estate Development. 7.8%, Due July 2027.
- Agua Residences By Citi Developers - Tower 1Also by Citi Developers Real Estate Development. 5.0%, Due December 2027.
- Arya Residences By Citi DevelopersAlso by Citi Developers Real Estate Development. 3.0%, Due December 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)