Skip to content

Agua Residences By Citi Developers - Tower 2 construction progress

The registered completion date for Agua Residences By Citi Developers - Tower 2 in Palm Deira is December 2027. At the last site inspection, in September 2026, it was 3.1% built. The developer is Citi Developers Real Estate Development.

3.1%

Built, at the site inspection of 15 September 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
November 2047
Construction started
August 2025
First registered
June 2025
Community
Palm Deira
Units
61
Escrow bank
The National Bank of Fujairah
Name in Arabic
أغوا ريزيدنسز من سيتي ديفيلوبرز - تاور 2
Project number
3756
Site inspections
4

Schedule

Between January 2026 and September 2026 the site added about 0.4 points a month. At that rate it would finish around November 2047, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 September 2026

3.1%+0.7 pts

  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 1, 15 September 2026
  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 2, 15 September 2026
  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 3, 15 September 2026
  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 4, 15 September 2026

29 April 2026

2.5%+2.4 pts

  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 1, 29 April 2026
  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 2, 29 April 2026
  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 3, 29 April 2026
  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 4, 29 April 2026

13 January 2026

0%+0.0 pts

  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 1, 13 January 2026
  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 2, 13 January 2026
  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 3, 13 January 2026
  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 4, 13 January 2026

3 June 2025

0%

  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 1, 3 June 2025
  • Agua Residences By Citi Developers - Tower 2 construction site, inspection photo 2, 3 June 2025

All 15 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Citi Developers Real Estate Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Agua Residences By Citi Developers - Tower 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Agua Residences By Citi Developers - Tower 2 handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2047. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Agua Residences By Citi Developers - Tower 2?
Agua Residences By Citi Developers - Tower 2 was 3.1% built at the site inspection on 15 September 2026. The site has been inspected 4 times since June 2025. The Land Department took 15 site photos at its inspections.
Is Agua Residences By Citi Developers - Tower 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Agua Residences By Citi Developers - Tower 2?
The registered developer is Citi Developers Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Agua Residences By Citi Developers - Tower 2?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.