Auresta Tower construction progress
Auresta Tower in Jumeirah Village Circle is 2.0% built at the Land Department inspection of July 2026. Developer Tiger Properties. Completion registered for December 2028.
2.0%
Built, at the Land Department site inspection of 27 July 2026
Running behind its date
- Completion date (Land Department)
- December 2028
- Finish at recent pace
- May 2053
- Construction started
- May 2025
- Registered with the Land Department
- June 2025
- Developer
- Tiger Properties
- Community
- Jumeirah Village Circle
- Units
- 840
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- برج أوريستا
- Land Department project number
- 3734
- Land Department site inspections
- 3
Schedule
Between January 2026 and July 2026 the site added about 0.3 points a month. At that rate it would finish around May 2053, more than three months after the December 2028 date registered with the Land Department.
Site inspections
27 July 2026
2.0%+2.0 pts
8 January 2026
0%
16 June 2025
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Tiger Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Auresta Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Auresta Tower be completed?
- The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around May 2053. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Auresta Tower is built?
- 2.0%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 3 times since June 2025.
- Is Auresta Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Auresta Tower?
- The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Auresta Tower?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tiger Sky TowerAlso by Tiger Properties. 10%.
- Altai TowerAlso by Tiger Properties. 98%, Due January 2026, passed.
- Volga TowerAlso by Tiger Properties. 51%.
- Red SquareAlso by Tiger Properties. 27%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)