Skip to content

Auresta Tower construction progress

Auresta Tower in Jumeirah Village Circle is 2.0% built at the Land Department inspection of July 2026. Developer Tiger Properties. Completion registered for December 2028.

2.0%

Built, at the Land Department site inspection of 27 July 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
May 2053
Construction started
May 2025
Registered with the Land Department
June 2025
Units
840
Escrow bank
First Abu Dhabi Bank
Name in Arabic
برج أوريستا
Land Department project number
3734
Land Department site inspections
3

Schedule

Between January 2026 and July 2026 the site added about 0.3 points a month. At that rate it would finish around May 2053, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

27 July 2026

2.0%+2.0 pts

  • Auresta Tower construction site, Land Department inspection photo 1, 27 July 2026
  • Auresta Tower construction site, Land Department inspection photo 2, 27 July 2026
  • Auresta Tower construction site, Land Department inspection photo 3, 27 July 2026
  • Auresta Tower construction site, Land Department inspection photo 4, 27 July 2026

8 January 2026

0%

  • Auresta Tower construction site, Land Department inspection photo 1, 8 January 2026
  • Auresta Tower construction site, Land Department inspection photo 2, 8 January 2026
  • Auresta Tower construction site, Land Department inspection photo 3, 8 January 2026
  • Auresta Tower construction site, Land Department inspection photo 4, 8 January 2026

16 June 2025

0%

  • Auresta Tower construction site, Land Department inspection photo 1, 16 June 2025
  • Auresta Tower construction site, Land Department inspection photo 2, 16 June 2025

All 10 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Tiger Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Auresta Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Auresta Tower be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around May 2053. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Auresta Tower is built?
2.0%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 3 times since June 2025.
Is Auresta Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Auresta Tower?
The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Auresta Tower?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.