Auresta Tower construction progress

The registered completion date for Auresta Tower in Jumeirah Village Circle is December 2028. At the last site inspection, in October 2026, it was 4.4% built. The developer is Tiger Properties.

4.4%

Built, at the site inspection of 8 October 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
November 2042
Construction started
May 2025
First registered
June 2025
Units
840
Escrow bank
First Abu Dhabi Bank
Name in Arabic
برج أوريستا
Project number
3734
Site inspections
4

Schedule

Between January 2026 and October 2026 the site added about 0.5 points a month. At that rate it would finish around November 2042, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 October 2026

4.4%+2.4 pts

  • Auresta Tower construction site, inspection photo 1, 8 October 2026
  • Auresta Tower construction site, inspection photo 2, 8 October 2026
  • Auresta Tower construction site, inspection photo 3, 8 October 2026

27 July 2026

2.0%+2.0 pts

  • Auresta Tower construction site, inspection photo 1, 27 July 2026
  • Auresta Tower construction site, inspection photo 2, 27 July 2026
  • Auresta Tower construction site, inspection photo 3, 27 July 2026
  • Auresta Tower construction site, inspection photo 4, 27 July 2026

8 January 2026

0%

  • Auresta Tower construction site, inspection photo 1, 8 January 2026
  • Auresta Tower construction site, inspection photo 2, 8 January 2026
  • Auresta Tower construction site, inspection photo 3, 8 January 2026
  • Auresta Tower construction site, inspection photo 4, 8 January 2026

16 June 2025

0%

  • Auresta Tower construction site, inspection photo 1, 16 June 2025
  • Auresta Tower construction site, inspection photo 2, 16 June 2025

All 13 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Tiger Properties has 8 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Auresta Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Auresta Tower handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2042. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Auresta Tower?
Auresta Tower was 4.4% built at the site inspection on 8 October 2026. The site has been inspected 4 times since June 2025. The Land Department took 13 site photos at its inspections.
Is Auresta Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Auresta Tower?
The registered developer is Tiger Properties. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Auresta Tower?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.