Samana Resorts construction progress

The registered completion date for Samana Resorts in International Media Production Zone is May 2028. At the last site inspection, in October 2026, it was 5.9% built. The developer is Samana International Real Estate Development.

5.9%

Built, at the site inspection of 22 October 2026

Running behind its date

Registered completion date
May 2028
Finish at recent pace
August 2058
Construction started
May 2025
First registered
January 2025
Units
969
Escrow bank
Dubai Islamic Bank
Name in Arabic
سامانا ريزورتس
Project number
2895
Site inspections
6

Schedule

Between November 2025 and October 2026 the site added about 0.2 points a month. At that rate it would finish around August 2058, more than three months after its registered date of May 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 October 2026

5.9%+0.0 pts

  • Samana Resorts construction site, inspection photo 1, 22 October 2026
  • Samana Resorts construction site, inspection photo 2, 22 October 2026
  • Samana Resorts construction site, inspection photo 3, 22 October 2026
  • Samana Resorts construction site, inspection photo 4, 22 October 2026

23 June 2026

5.8%+1.4 pts

  • Samana Resorts construction site, inspection photo 1, 23 June 2026
  • Samana Resorts construction site, inspection photo 2, 23 June 2026
  • Samana Resorts construction site, inspection photo 3, 23 June 2026
  • Samana Resorts construction site, inspection photo 4, 23 June 2026

3 April 2026

4.4%+1.4 pts

  • Samana Resorts construction site, inspection photo 1, 3 April 2026
  • Samana Resorts construction site, inspection photo 2, 3 April 2026
  • Samana Resorts construction site, inspection photo 3, 3 April 2026
  • Samana Resorts construction site, inspection photo 4, 3 April 2026

3 November 2025

3.0%+1.0 pts

  • Samana Resorts construction site, inspection photo 1, 3 November 2025
  • Samana Resorts construction site, inspection photo 2, 3 November 2025
  • Samana Resorts construction site, inspection photo 3, 3 November 2025
  • Samana Resorts construction site, inspection photo 4, 3 November 2025

17 June 2025

2.0%+2.0 pts

  • Samana Resorts construction site, inspection photo 1, 17 June 2025
  • Samana Resorts construction site, inspection photo 2, 17 June 2025
  • Samana Resorts construction site, inspection photo 3, 17 June 2025

7 March 2024

0%

  • Samana Resorts construction site, inspection photo 1, 7 March 2024
  • Samana Resorts construction site, inspection photo 2, 7 March 2024
  • Samana Resorts construction site, inspection photo 3, 7 March 2024

All 25 site photos, by inspection date

Context

International Media Production Zone has 15 projects under construction, 23% built on average.

Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Samana Resorts?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Resorts handover date?
The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2058. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Samana Resorts?
Samana Resorts was 5.9% built at the site inspection on 22 October 2026. The site has been inspected 6 times since March 2024. The Land Department took 25 site photos at its inspections.
Is Samana Resorts delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Samana Resorts?
The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Resorts?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.