Golf Grove By Regent construction progress

Golf Grove By Regent in International Media Production Zone is 8.7% built at the Land Department inspection of June 2026. Developer Regent Star Property Developments. Completion registered for January 2028.

8.7%

Built, at the Land Department site inspection of 10 June 2026

Running behind its date

Completion date (Land Department)
January 2028
Finish at recent pace
October 2032
Construction started
January 2025
Registered with the Land Department
February 2025
Developer
Regent Star Property Developments
Units
98
Escrow bank
Emirates NBD
Name in Arabic
جولف جروف باي ريجنت
Land Department project number
3245
Land Department site inspections
3

Schedule

Between November 2025 and June 2026 the site added about 1.2 points a month. At that rate it would finish around October 2032, more than three months after the January 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 June 2026

8.7%+8.3 pts

  • Golf Grove By Regent construction site, Land Department inspection photo 1, 10 June 2026
  • Golf Grove By Regent construction site, Land Department inspection photo 2, 10 June 2026
  • Golf Grove By Regent construction site, Land Department inspection photo 3, 10 June 2026
  • Golf Grove By Regent construction site, Land Department inspection photo 4, 10 June 2026

11 November 2025

0.4%+0.4 pts

  • Golf Grove By Regent construction site, Land Department inspection photo 1, 11 November 2025
  • Golf Grove By Regent construction site, Land Department inspection photo 2, 11 November 2025
  • Golf Grove By Regent construction site, Land Department inspection photo 3, 11 November 2025
  • Golf Grove By Regent construction site, Land Department inspection photo 4, 11 November 2025

13 January 2025

0%

  • Golf Grove By Regent construction site, Land Department inspection photo 1, 13 January 2025
  • Golf Grove By Regent construction site, Land Department inspection photo 2, 13 January 2025

All 11 site photos, by inspection date

Context

International Media Production Zone has 15 projects under construction, 22% built on average.

Own a unit in Golf Grove By Regent?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Golf Grove By Regent be completed?
The completion date registered with the Dubai Land Department is January 2028. At the pace of its recent inspections the site would reach 100% around October 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Golf Grove By Regent is built?
8.7%, measured at the Land Department site inspection on 10 June 2026. The Land Department engineers have inspected the site 3 times since January 2025.
Is Golf Grove By Regent delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
Who is building Golf Grove By Regent?
The registered developer is Regent Star Property Developments.
Which bank holds the escrow account for Golf Grove By Regent?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.