Golf Grove By Regent construction progress
The registered completion date for Golf Grove By Regent in International Media Production Zone is January 2028. At the last site inspection, in June 2026, it was 8.7% built. The developer is Regent Star Property Developments.
8.7%
Built, at the site inspection of 10 June 2026
Running behind its date
- Registered completion date
- January 2028
- Finish at recent pace
- October 2032
- Construction started
- January 2025
- First registered
- February 2025
- Developer
- Regent Star Property Developments
- Community
- International Media Production Zone
- Units
- 98
- Escrow bank
- Emirates NBD
- Name in Arabic
- جولف جروف باي ريجنت
- Project number
- 3245
- Site inspections
- 3
Schedule
Between November 2025 and June 2026 the site added about 1.2 points a month. At that rate it would finish around October 2032, more than three months after its registered date of January 2028.
Site inspections
10 June 2026
8.7%+8.3 pts
11 November 2025
0.4%+0.4 pts
13 January 2025
0%
Context
International Media Production Zone has 15 projects under construction, 23% built on average.
Own a unit in Golf Grove By Regent?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Golf Grove By Regent handover date?
- The registered completion date is January 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Golf Grove By Regent?
- Golf Grove By Regent was 8.7% built at the site inspection on 10 June 2026. The site has been inspected 3 times since January 2025. The Land Department took 11 site photos at its inspections.
- Is Golf Grove By Regent delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
- Who is building Golf Grove By Regent?
- The registered developer is Regent Star Property Developments.
- Which bank holds the escrow account for Golf Grove By Regent?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana PortofinoNearby in International Media Production Zone. 60%.
- Samana ResortsNearby in International Media Production Zone. 5.9%, Due May 2028.
- Samana Lake ViewsNearby in International Media Production Zone. 23%.
- Samana Lake Views 2Nearby in International Media Production Zone. 12%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.