Imperial Residence construction progress

Imperial Residence in International Media Production Zone is 43% built at the Land Department inspection of January 2026. Developer Imperial 55 Real Estate Development. Completion registered for April 2026.

43%

Built, at the Land Department site inspection of 5 January 2026

5 months past its registered completion date

Completion date (Land Department)
April 2026
Finish at recent pace
October 2027
Construction started
June 2024
Registered with the Land Department
December 2024
Developer
Imperial 55 Real Estate Development
Units
137
Escrow bank
Emirates NBD
Name in Arabic
امبريال ريزيدنس
Land Department project number
3217
Land Department site inspections
5

Schedule

Imperial Residence was registered to complete in April 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around October 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

5 January 2026

43%+22 pts

  • Imperial Residence construction site, Land Department inspection photo 1, 5 January 2026
  • Imperial Residence construction site, Land Department inspection photo 2, 5 January 2026
  • Imperial Residence construction site, Land Department inspection photo 3, 5 January 2026
  • Imperial Residence construction site, Land Department inspection photo 4, 5 January 2026

2 June 2025

21%+6.4 pts

  • Imperial Residence construction site, Land Department inspection photo 1, 2 June 2025
  • Imperial Residence construction site, Land Department inspection photo 2, 2 June 2025
  • Imperial Residence construction site, Land Department inspection photo 3, 2 June 2025
  • Imperial Residence construction site, Land Department inspection photo 4, 2 June 2025

17 February 2025

14%+2.2 pts

  • Imperial Residence construction site, Land Department inspection photo 1, 17 February 2025
  • Imperial Residence construction site, Land Department inspection photo 2, 17 February 2025
  • Imperial Residence construction site, Land Department inspection photo 3, 17 February 2025
  • Imperial Residence construction site, Land Department inspection photo 4, 17 February 2025

23 January 2025

12%+12 pts

  • Imperial Residence construction site, Land Department inspection photo 1, 23 January 2025
  • Imperial Residence construction site, Land Department inspection photo 2, 23 January 2025
  • Imperial Residence construction site, Land Department inspection photo 3, 23 January 2025

7 October 2024

0%

  • Imperial Residence construction site, Land Department inspection photo 1, 7 October 2024
  • Imperial Residence construction site, Land Department inspection photo 2, 7 October 2024

All 23 site photos, by inspection date

Context

International Media Production Zone has 15 projects under construction, 22% built on average.

Own a unit in Imperial Residence?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Imperial Residence be completed?
The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Imperial Residence is built?
43%, measured at the Land Department site inspection on 5 January 2026. The Land Department engineers have inspected the site 5 times since October 2024.
Is Imperial Residence delayed?
Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
Who is building Imperial Residence?
The registered developer is Imperial 55 Real Estate Development.
Which bank holds the escrow account for Imperial Residence?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.