Neem At Park Five construction progress
The registered completion date for Neem At Park Five in International Media Production Zone is December 2027. At the last site inspection, in September 2026, it was 15% built. The developer is Deyaar Development.
15%
Built, at the site inspection of 9 September 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- April 2031
- Construction started
- July 2025
- First registered
- April 2025
- Developer
- Deyaar Development
- Community
- International Media Production Zone
- Units
- 145
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- نيم في بارك فايف
- Project number
- 3496
- Site inspections
- 3
Schedule
Between June 2026 and September 2026 the site added about 1.5 points a month. At that rate it would finish around April 2031, more than three months after its registered date of December 2027.
Site inspections
9 September 2026
15%+4.6 pts
10 June 2026
11%+11 pts
16 January 2025
0%
Context
International Media Production Zone has 15 projects under construction, 23% built on average.
Deyaar Development has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Neem At Park Five?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Neem At Park Five handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Neem At Park Five?
- Neem At Park Five was 15% built at the site inspection on 9 September 2026. The site has been inspected 3 times since January 2025. The Land Department took 13 site photos at its inspections.
- Is Neem At Park Five delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Neem At Park Five?
- The registered developer is Deyaar Development. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Neem At Park Five?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mar CasaAlso by Deyaar Development. 67%, Due October 2026, passed.
- Rosalia ResidencesAlso by Deyaar Development. 93%.
- Eleve By DeyaarAlso by Deyaar Development. 20%.
- Elm At Park FiveAlso by Deyaar Development. 16%, Due June 2027.
- Samana PortofinoNearby in International Media Production Zone. 60%.
- Samana ResortsNearby in International Media Production Zone. 5.9%, Due May 2028.
- Samana Lake ViewsNearby in International Media Production Zone. 23%.
- Samana Lake Views 2Nearby in International Media Production Zone. 12%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.