Neem At Park Five construction progress

Neem At Park Five in International Media Production Zone is 15% built at the Land Department inspection of September 2026. Developer Deyaar Development. Completion registered for December 2027.

15%

Built, at the Land Department site inspection of 9 September 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
April 2031
Construction started
July 2025
Registered with the Land Department
April 2025
Units
145
Escrow bank
Dubai Islamic Bank
Name in Arabic
نيم في بارك فايف
Land Department project number
3496
Land Department site inspections
3

Schedule

Between June 2026 and September 2026 the site added about 1.5 points a month. At that rate it would finish around April 2031, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 September 2026

15%+4.6 pts

  • Neem At Park Five construction site, Land Department inspection photo 1, 9 September 2026
  • Neem At Park Five construction site, Land Department inspection photo 2, 9 September 2026
  • Neem At Park Five construction site, Land Department inspection photo 3, 9 September 2026
  • Neem At Park Five construction site, Land Department inspection photo 4, 9 September 2026

10 June 2026

11%+11 pts

  • Neem At Park Five construction site, Land Department inspection photo 1, 10 June 2026
  • Neem At Park Five construction site, Land Department inspection photo 2, 10 June 2026
  • Neem At Park Five construction site, Land Department inspection photo 3, 10 June 2026
  • Neem At Park Five construction site, Land Department inspection photo 4, 10 June 2026

16 January 2025

0%

  • Neem At Park Five construction site, Land Department inspection photo 1, 16 January 2025
  • Neem At Park Five construction site, Land Department inspection photo 2, 16 January 2025
  • Neem At Park Five construction site, Land Department inspection photo 3, 16 January 2025

All 13 site photos, by inspection date

Context

International Media Production Zone has 15 projects under construction, 22% built on average.

Deyaar Development has 10 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Neem At Park Five?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Neem At Park Five be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around April 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Neem At Park Five is built?
15%, measured at the Land Department site inspection on 9 September 2026. The Land Department engineers have inspected the site 3 times since January 2025.
Is Neem At Park Five delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Neem At Park Five?
The registered developer is Deyaar Development. It has 9 other projects under construction in Dubai.
Which bank holds the escrow account for Neem At Park Five?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.