South Bay 1 construction progress

South Bay 1 in Dubai South Residential District was registered to complete in March 2025 and is still under construction. At the last site inspection, in July 2026, it was 94% built. The developer is Dubai South Properties Dwc.

94%

Built, at the site inspection of 23 July 2026

21 months past its registered completion date

Registered completion date
March 2025
Finish at recent pace
June 2027
Construction started
March 2023
First registered
September 2022
Units
251
Escrow bank
Dubai Islamic Bank
Name in Arabic
1 خليج الجنوب
Project number
2452
Site inspections
5

Schedule

South Bay 1 was registered to complete in March 2025, 21 months ago, and is still under construction. Over the last year of inspections it has added about 0.6 points a month. Kept at that rate, the site would reach 100% around June 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 July 2026

94%+1.7 pts

  • South Bay 1 construction site, inspection photo 1, 23 July 2026
  • South Bay 1 construction site, inspection photo 2, 23 July 2026
  • South Bay 1 construction site, inspection photo 3, 23 July 2026
  • South Bay 1 construction site, inspection photo 4, 23 July 2026

25 April 2026

92%+1.4 pts

  • South Bay 1 construction site, inspection photo 1, 25 April 2026
  • South Bay 1 construction site, inspection photo 2, 25 April 2026
  • South Bay 1 construction site, inspection photo 3, 25 April 2026
  • South Bay 1 construction site, inspection photo 4, 25 April 2026

11 July 2025

91%+29 pts

  • South Bay 1 construction site, inspection photo 1, 11 July 2025
  • South Bay 1 construction site, inspection photo 2, 11 July 2025
  • South Bay 1 construction site, inspection photo 3, 11 July 2025
  • South Bay 1 construction site, inspection photo 4, 11 July 2025

18 October 2024

61%+61 pts

  • South Bay 1 construction site, inspection photo 1, 18 October 2024
  • South Bay 1 construction site, inspection photo 2, 18 October 2024
  • South Bay 1 construction site, inspection photo 3, 18 October 2024
  • South Bay 1 construction site, inspection photo 4, 18 October 2024

20 September 2022

0%

  • South Bay 1 construction site, inspection photo 1, 20 September 2022
  • South Bay 1 construction site, inspection photo 2, 20 September 2022
  • South Bay 1 construction site, inspection photo 3, 20 September 2022

All 37 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Dubai South Properties Dwc has 19 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in South Bay 1?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the South Bay 1 handover date?
The registered completion date was March 2025, and the register still lists South Bay 1 as under construction. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on South Bay 1?
South Bay 1 was 94% built at the site inspection on 23 July 2026. The site has been inspected 5 times since September 2022. The Land Department took 37 site photos at its inspections.
Is South Bay 1 delayed?
Yes. Its registered completion date of March 2025 has passed and the project is still listed as under construction.
Who is building South Bay 1?
The registered developer is Dubai South Properties Dwc. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for South Bay 1?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.