South Bay 1 construction progress
South Bay 1 in Dubai South Residential District was registered to complete in March 2025 and is still under construction. At the last site inspection, in July 2026, it was 94% built. The developer is Dubai South Properties Dwc.
94%
Built, at the site inspection of 23 July 2026
21 months past its registered completion date
- Registered completion date
- March 2025
- Finish at recent pace
- June 2027
- Construction started
- March 2023
- First registered
- September 2022
- Developer
- Dubai South Properties Dwc
- Community
- Dubai South Residential District
- Units
- 251
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- 1 خليج الجنوب
- Project number
- 2452
- Site inspections
- 5
Schedule
South Bay 1 was registered to complete in March 2025, 21 months ago, and is still under construction. Over the last year of inspections it has added about 0.6 points a month. Kept at that rate, the site would reach 100% around June 2027.
Site inspections
23 July 2026
94%+1.7 pts
25 April 2026
92%+1.4 pts
11 July 2025
91%+29 pts
18 October 2024
61%+61 pts
20 September 2022
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Dubai South Properties Dwc has 19 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in South Bay 1?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the South Bay 1 handover date?
- The registered completion date was March 2025, and the register still lists South Bay 1 as under construction. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on South Bay 1?
- South Bay 1 was 94% built at the site inspection on 23 July 2026. The site has been inspected 5 times since September 2022. The Land Department took 37 site photos at its inspections.
- Is South Bay 1 delayed?
- Yes. Its registered completion date of March 2025 has passed and the project is still listed as under construction.
- Who is building South Bay 1?
- The registered developer is Dubai South Properties Dwc. It has 18 other projects under construction in Dubai.
- Which bank holds the escrow account for South Bay 1?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Bay 2Also by Dubai South Properties Dwc. 94%, Due May 2026, passed.
- South Bay 3 PremiumAlso by Dubai South Properties Dwc. 88%.
- South Bay 4 PremiumAlso by Dubai South Properties Dwc. 86%.
- South Bay 5 PremiumAlso by Dubai South Properties Dwc. 78%.
- Lincoln Star ResidenceNearby in Dubai South Residential District. 55%, Due September 2026, passed.
- Views VII By Golden WoodsNearby in Dubai South Residential District. 90%, Due July 2026, passed.
- Voi Residence By Hvm LivingNearby in Dubai South Residential District. 20%, Due September 2026, passed.
- The Eighty ThreeNearby in Dubai South Residential District. 60%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.