Dubai South Properties Dwc projects under construction
Dubai South Properties Dwc has 19 projects under construction in Dubai. On average they are 33% built. 2 have passed their registered completion date. The next one due is Beachfront Gates 2, in December 2026.
- South Bay 2Dubai South Residential District94%Due May 2026, passed
- South Bay 1Dubai South Residential District94%Due March 2025, passed
- South Bay 3 PremiumDubai South Residential District88%No date set
- South Bay 4 PremiumDubai South Residential District86%No date set
- South Bay 6 PremiumDubai South Residential District82%No date set
- South Bay 5 PremiumDubai South Residential District78%No date set
- Beachfront Gates 2Dubai South Residential District61%Due December 2026
- Beachfront Gates 1Dubai South Residential District36%Due December 2026
- Hayat 4Dubai World Central4.5%Due July 2028
- Hayat 3Dubai World Central3.9%Due May 2028
- Hayat 5Dubai World Central3.2%Due July 2028
- South SquareDubai World Central2.6%Due June 2028
- Hayat 2Dubai World Central2.0%Due May 2028
- Beachfront Gates 30%Due May 2029
- Hayat 10%Due March 2029
- Hayat 60%Due March 2029
- Hayat 70%Due March 2029
- Hayat 80%Due April 2030
- Hayat 90%Due April 2030
Questions
How many projects is Dubai South Properties Dwc building in Dubai?
19 projects are under construction, 33% built on average at the latest site inspections.
Which Dubai South Properties Dwc projects finish next?
By registered completion date: Beachfront Gates 2 (December 2026, 61% built), Beachfront Gates 1 (December 2026, 36% built) and Hayat 3 (May 2028, 3.9% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
Are any Dubai South Properties Dwc projects delayed?
2 of its 19 projects have passed the registered completion date, among them South Bay 1 and South Bay 2. A project counts as late once its registered completion date has passed before it reaches 100%.
Where is Dubai South Properties Dwc building?
Its projects are in Dubai South Residential District (8) and Dubai World Central (5).
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.