South Bay 3 Premium construction progress
South Bay 3 Premium in Dubai South Residential District is 88% built at the Land Department inspection of July 2026. Developer Dubai South Properties Dwc.
88%
Built, at the Land Department site inspection of 23 July 2026
- Finish at recent pace
- October 2026
- Construction started
- December 2023
- Registered with the Land Department
- September 2023
- Developer
- Dubai South Properties Dwc
- Community
- Dubai South Residential District
- Units
- 213
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- خليج الجنوب 3 بريميوم
- Land Department project number
- 2711
- Land Department site inspections
- 5
Schedule
Since July 2025 South Bay 3 Premium has added about 3.7 points a month. At that rate the site reaches 100% around October 2026. The Land Department has no completion date on record to compare it with.
Site inspections
23 July 2026
88%+25 pts
11 February 2026
63%+19 pts
23 July 2025
44%+35 pts
18 December 2024
9.0%+9.0 pts
14 August 2023
0%
Context
Dubai South Residential District has 40 projects under construction, 40% built on average.
Dubai South Properties Dwc has 17 projects under construction in Dubai, none past their registered completion dates.
Own a unit in South Bay 3 Premium?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will South Bay 3 Premium be completed?
- The Land Department has no completion date on record for South Bay 3 Premium yet.
- How much of South Bay 3 Premium is built?
- 88%, measured at the Land Department site inspection on 23 July 2026. The Land Department engineers have inspected the site 5 times since August 2023.
- Who is building South Bay 3 Premium?
- The registered developer is Dubai South Properties Dwc. It has 16 other projects under construction in Dubai.
- Which bank holds the escrow account for South Bay 3 Premium?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South LivingAlso by Dubai South Properties Dwc. 89%.
- South Bay 1Also by Dubai South Properties Dwc. 94%.
- South Bay 2Also by Dubai South Properties Dwc. 94%.
- South Bay 4 PremiumAlso by Dubai South Properties Dwc. 86%.
- Lincoln Star ResidenceNearby in Dubai South Residential District. 47%, Due September 2026, passed.
- The HarmonyNearby in Dubai South Residential District. 85%, Due October 2025, passed.
- Views Vii By Golden WoodsNearby in Dubai South Residential District. 90%, Due July 2026, passed.
- Voi Residence By Hvm LivingNearby in Dubai South Residential District. 16%, Due September 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.