South Bay 3 Premium construction progress

No completion date is registered for South Bay 3 Premium in Dubai South Residential District yet. At the last site inspection, in July 2026, it was 88% built. The developer is Dubai South Properties Dwc.

88%

Built, at the site inspection of 23 July 2026

Finish at recent pace
October 2026
Construction started
December 2023
First registered
September 2023
Units
213
Escrow bank
Emirates Islamic Bank
Name in Arabic
خليج الجنوب 3 بريميوم
Project number
2711
Site inspections
5

Schedule

Since July 2025 South Bay 3 Premium has added about 3.7 points a month. At that rate the site reaches 100% around October 2026. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

23 July 2026

88%+25 pts

  • South Bay 3 Premium construction site, inspection photo 1, 23 July 2026
  • South Bay 3 Premium construction site, inspection photo 2, 23 July 2026
  • South Bay 3 Premium construction site, inspection photo 3, 23 July 2026
  • South Bay 3 Premium construction site, inspection photo 4, 23 July 2026

11 February 2026

63%+19 pts

  • South Bay 3 Premium construction site, inspection photo 1, 11 February 2026
  • South Bay 3 Premium construction site, inspection photo 2, 11 February 2026
  • South Bay 3 Premium construction site, inspection photo 3, 11 February 2026
  • South Bay 3 Premium construction site, inspection photo 4, 11 February 2026

23 July 2025

44%+35 pts

  • South Bay 3 Premium construction site, inspection photo 1, 23 July 2025
  • South Bay 3 Premium construction site, inspection photo 2, 23 July 2025
  • South Bay 3 Premium construction site, inspection photo 3, 23 July 2025
  • South Bay 3 Premium construction site, inspection photo 4, 23 July 2025

18 December 2024

9.0%+9.0 pts

  • South Bay 3 Premium construction site, inspection photo 1, 18 December 2024
  • South Bay 3 Premium construction site, inspection photo 2, 18 December 2024
  • South Bay 3 Premium construction site, inspection photo 3, 18 December 2024
  • South Bay 3 Premium construction site, inspection photo 4, 18 December 2024

14 August 2023

0%

  • South Bay 3 Premium construction site, inspection photo 1, 14 August 2023
  • South Bay 3 Premium construction site, inspection photo 2, 14 August 2023

All 34 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Dubai South Properties Dwc has 19 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in South Bay 3 Premium?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the South Bay 3 Premium handover date?
No completion date is on record for South Bay 3 Premium yet. Handover follows completion, so there is no date to give.
What is the latest construction update on South Bay 3 Premium?
South Bay 3 Premium was 88% built at the site inspection on 23 July 2026. The site has been inspected 5 times since August 2023. The Land Department took 34 site photos at its inspections.
Who is building South Bay 3 Premium?
The registered developer is Dubai South Properties Dwc. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for South Bay 3 Premium?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.