Glitz Residence 3 construction progress
The register lists Glitz Residence 3 in Dubai Studio City as complete, with a registered completion date of February 2018. Its last site inspection on record was in July 2018. The developer is Danube Properties Development.
100%
Built, at the site inspection of 23 July 2018
Construction complete
- Registered completion date
- February 2018
- Construction started
- June 2015
- First registered
- April 2015
- Developer
- Danube Properties Development
- Community
- Dubai Studio City
- Units
- 358
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- جليتز ريزيدنس 3
- Project number
- 1655
- Site inspections
- 9
Schedule
The register lists Glitz Residence 3 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
23 July 2018
100%+6.3 pts
5 March 2018
94%+5.4 pts
7 January 2018
88%+8.2 pts
2 November 2017
80%+8.5 pts
17 September 2017
72%+25 pts
28 March 2017
47%+26 pts
14 November 2016
21%+5.6 pts
22 August 2016
15%+14 pts
7 September 2015
0.8%
Context
Dubai Studio City has 8 projects under construction, 53% built on average.
Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Glitz Residence 3?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Glitz Residence 3 handover date?
- Construction of Glitz Residence 3 is recorded as complete, with a registered completion date of February 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Glitz Residence 3?
- Glitz Residence 3 was 100% built at the site inspection on 23 July 2018. The site has been inspected 9 times since September 2015. The Land Department took 55 site photos at its inspections.
- Is Glitz Residence 3 delayed?
- The register lists construction as complete.
- Who is building Glitz Residence 3?
- The registered developer is Danube Properties Development. It has 23 other projects under construction in Dubai.
- Which bank holds the escrow account for Glitz Residence 3?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elitz By DanubeAlso by Danube Properties Development. 92%, Due December 2025, passed.
- Viewz 1 By DanubeAlso by Danube Properties Development. 66%, Due June 2026, passed.
- Viewz 2 By DanubeAlso by Danube Properties Development. 65%, Due June 2026, passed.
- Fashionz 1 By DanubeAlso by Danube Properties Development. 40%.
- Samana MykonosNearby in Dubai Studio City. 91%, Due April 2026, passed.
- Laya CourtyardNearby in Dubai Studio City. 51%, Due December 2026.
- Beach Oasis 2Nearby in Dubai Studio City. 57%, Due April 2026, passed.
- Arisha TerracesNearby in Dubai Studio City. 34%, Due October 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)