Viewz 1 By Danube construction progress

Viewz 1 By Danube in Jumeirah Lakes Towers is 50% built at the Land Department inspection of July 2026. Developer Danube Properties Development. Completion registered for June 2026.

50%

Built, at the Land Department site inspection of 21 July 2026

3 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
February 2028
Construction started
July 2023
Registered with the Land Department
April 2023
Units
564
Escrow bank
First Abu Dhabi Bank
Name in Arabic
فيوز 1 من دانوب
Land Department project number
2554
Land Department site inspections
10

Schedule

Viewz 1 By Danube was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around February 2028.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

21 July 2026

50%+10.0 pts

  • Viewz 1 By Danube construction site, Land Department inspection photo 1, 21 July 2026
  • Viewz 1 By Danube construction site, Land Department inspection photo 2, 21 July 2026
  • Viewz 1 By Danube construction site, Land Department inspection photo 3, 21 July 2026
  • Viewz 1 By Danube construction site, Land Department inspection photo 4, 21 July 2026

23 April 2026

40%+10 pts

  • Viewz 1 By Danube construction site, Land Department inspection photo 1, 23 April 2026
  • Viewz 1 By Danube construction site, Land Department inspection photo 2, 23 April 2026
  • Viewz 1 By Danube construction site, Land Department inspection photo 3, 23 April 2026
  • Viewz 1 By Danube construction site, Land Department inspection photo 4, 23 April 2026

14 January 2026

30%+5.0 pts

  • Viewz 1 By Danube construction site, Land Department inspection photo 1, 14 January 2026
  • Viewz 1 By Danube construction site, Land Department inspection photo 2, 14 January 2026
  • Viewz 1 By Danube construction site, Land Department inspection photo 3, 14 January 2026
  • Viewz 1 By Danube construction site, Land Department inspection photo 4, 14 January 2026

10 October 2025

25%+4.5 pts

  • Viewz 1 By Danube construction site, Land Department inspection photo 1, 10 October 2025
  • Viewz 1 By Danube construction site, Land Department inspection photo 2, 10 October 2025
  • Viewz 1 By Danube construction site, Land Department inspection photo 3, 10 October 2025
  • Viewz 1 By Danube construction site, Land Department inspection photo 4, 10 October 2025

10 July 2025

21%+6.9 pts

  • Viewz 1 By Danube construction site, Land Department inspection photo 1, 10 July 2025
  • Viewz 1 By Danube construction site, Land Department inspection photo 2, 10 July 2025
  • Viewz 1 By Danube construction site, Land Department inspection photo 3, 10 July 2025
  • Viewz 1 By Danube construction site, Land Department inspection photo 4, 10 July 2025

3 April 2025

14%+7.1 pts

  • Viewz 1 By Danube construction site, Land Department inspection photo 1, 3 April 2025
  • Viewz 1 By Danube construction site, Land Department inspection photo 2, 3 April 2025
  • Viewz 1 By Danube construction site, Land Department inspection photo 3, 3 April 2025

11 December 2024

6.5%+6.2 pts

  • Viewz 1 By Danube construction site, Land Department inspection photo 1, 11 December 2024
  • Viewz 1 By Danube construction site, Land Department inspection photo 2, 11 December 2024
  • Viewz 1 By Danube construction site, Land Department inspection photo 3, 11 December 2024
  • Viewz 1 By Danube construction site, Land Department inspection photo 4, 11 December 2024

6 March 2024

0.3%+0.2 pts

  • Viewz 1 By Danube construction site, Land Department inspection photo 1, 6 March 2024
  • Viewz 1 By Danube construction site, Land Department inspection photo 2, 6 March 2024
  • Viewz 1 By Danube construction site, Land Department inspection photo 3, 6 March 2024

16 May 2023

0%+0.0 pts

  • Viewz 1 By Danube construction site, Land Department inspection photo 1, 16 May 2023
  • Viewz 1 By Danube construction site, Land Department inspection photo 2, 16 May 2023
  • Viewz 1 By Danube construction site, Land Department inspection photo 3, 16 May 2023
  • Viewz 1 By Danube construction site, Land Department inspection photo 4, 16 May 2023

10 January 2023

0%

  • Viewz 1 By Danube construction site, Land Department inspection photo 1, 10 January 2023
  • Viewz 1 By Danube construction site, Land Department inspection photo 2, 10 January 2023
  • Viewz 1 By Danube construction site, Land Department inspection photo 3, 10 January 2023

All 53 site photos, by inspection date

Context

Jumeirah Lakes Towers has 8 projects under construction, 44% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Viewz 1 By Danube?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Viewz 1 By Danube be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Viewz 1 By Danube is built?
50%, measured at the Land Department site inspection on 21 July 2026. The Land Department engineers have inspected the site 10 times since January 2023.
Is Viewz 1 By Danube delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Viewz 1 By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Viewz 1 By Danube?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.