Elitz By Danube construction progress

Elitz By Danube in Jumeirah Village Circle is 81% built at the Land Department inspection of August 2026. Developer Danube Properties Development. Completion registered for December 2025.

81%

Built, at the Land Department site inspection of 13 August 2026

9 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
December 2026
Construction started
May 2023
Registered with the Land Department
December 2022
Units
592
Escrow bank
United Bank Limited
Name in Arabic
إليتز من دانوب
Land Department project number
2533
Land Department site inspections
13

Schedule

Elitz By Danube was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 4.3 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 August 2026

81%+8.5 pts

  • Elitz By Danube construction site, Land Department inspection photo 1, 13 August 2026
  • Elitz By Danube construction site, Land Department inspection photo 2, 13 August 2026
  • Elitz By Danube construction site, Land Department inspection photo 3, 13 August 2026
  • Elitz By Danube construction site, Land Department inspection photo 4, 13 August 2026

6 July 2026

72%+8.2 pts

  • Elitz By Danube construction site, Land Department inspection photo 1, 6 July 2026
  • Elitz By Danube construction site, Land Department inspection photo 2, 6 July 2026
  • Elitz By Danube construction site, Land Department inspection photo 3, 6 July 2026
  • Elitz By Danube construction site, Land Department inspection photo 4, 6 July 2026

30 April 2026

64%+16 pts

  • Elitz By Danube construction site, Land Department inspection photo 1, 30 April 2026
  • Elitz By Danube construction site, Land Department inspection photo 2, 30 April 2026
  • Elitz By Danube construction site, Land Department inspection photo 3, 30 April 2026
  • Elitz By Danube construction site, Land Department inspection photo 4, 30 April 2026

24 December 2025

49%+16 pts

  • Elitz By Danube construction site, Land Department inspection photo 1, 24 December 2025
  • Elitz By Danube construction site, Land Department inspection photo 2, 24 December 2025
  • Elitz By Danube construction site, Land Department inspection photo 3, 24 December 2025
  • Elitz By Danube construction site, Land Department inspection photo 4, 24 December 2025

4 September 2025

33%+8.4 pts

  • Elitz By Danube construction site, Land Department inspection photo 1, 4 September 2025
  • Elitz By Danube construction site, Land Department inspection photo 2, 4 September 2025
  • Elitz By Danube construction site, Land Department inspection photo 3, 4 September 2025
  • Elitz By Danube construction site, Land Department inspection photo 4, 4 September 2025

2 June 2025

25%+10 pts

  • Elitz By Danube construction site, Land Department inspection photo 1, 2 June 2025
  • Elitz By Danube construction site, Land Department inspection photo 2, 2 June 2025
  • Elitz By Danube construction site, Land Department inspection photo 3, 2 June 2025
  • Elitz By Danube construction site, Land Department inspection photo 4, 2 June 2025

16 December 2024

15%+6.6 pts

  • Elitz By Danube construction site, Land Department inspection photo 1, 16 December 2024
  • Elitz By Danube construction site, Land Department inspection photo 2, 16 December 2024
  • Elitz By Danube construction site, Land Department inspection photo 3, 16 December 2024
  • Elitz By Danube construction site, Land Department inspection photo 4, 16 December 2024

20 August 2024

8.0%+2.2 pts

  • Elitz By Danube construction site, Land Department inspection photo 1, 20 August 2024
  • Elitz By Danube construction site, Land Department inspection photo 2, 20 August 2024
  • Elitz By Danube construction site, Land Department inspection photo 3, 20 August 2024
  • Elitz By Danube construction site, Land Department inspection photo 4, 20 August 2024

13 April 2024

5.8%+4.1 pts

  • Elitz By Danube construction site, Land Department inspection photo 1, 13 April 2024
  • Elitz By Danube construction site, Land Department inspection photo 2, 13 April 2024
  • Elitz By Danube construction site, Land Department inspection photo 3, 13 April 2024
  • Elitz By Danube construction site, Land Department inspection photo 4, 13 April 2024

28 December 2023

1.7%+0.9 pts

  • Elitz By Danube construction site, Land Department inspection photo 1, 28 December 2023
  • Elitz By Danube construction site, Land Department inspection photo 2, 28 December 2023
  • Elitz By Danube construction site, Land Department inspection photo 3, 28 December 2023
  • Elitz By Danube construction site, Land Department inspection photo 4, 28 December 2023

All 98 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Elitz By Danube?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Elitz By Danube be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Elitz By Danube is built?
81%, measured at the Land Department site inspection on 13 August 2026. The Land Department engineers have inspected the site 13 times since December 2022.
Is Elitz By Danube delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Elitz By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Elitz By Danube?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.