Glitz Residence 3 construction photos

55 photos from 9 site inspections, newest first. The percentage is how much of Glitz Residence 3 was built on the day of each visit.

23 July 2018100% built

5 March 201894% built

7 January 201888% built

2 November 201780% built

17 September 201772% built

28 March 201747% built

14 November 201621% built

22 August 201615% built

7 September 20150.8% built

Back to Glitz Residence 3 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.