The First Collection At Dubai Studio City construction progress

The First Collection At Dubai Studio City in Dubai Studio City is 21% built at the Land Department inspection of July 2026. Developer Tfg S C Development. Completion registered for January 2028.

21%

Built, at the Land Department site inspection of 13 July 2026

Running behind its date

Completion date (Land Department)
January 2028
Finish at recent pace
August 2029
Construction started
February 2025
Registered with the Land Department
February 2025
Developer
Tfg S C Development
Units
553
Escrow bank
Arab Bank
Name in Arabic
ذا فيرست كولكشن ات دبي ستوديو سيتي
Land Department project number
3370
Land Department site inspections
6

Schedule

Between November 2025 and July 2026 the site added about 2.1 points a month. At that rate it would finish around August 2029, more than three months after the January 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 July 2026

21%+9.2 pts

  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 1, 13 July 2026
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 2, 13 July 2026
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 3, 13 July 2026
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 4, 13 July 2026

27 March 2026

12%+6.0 pts

  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 1, 27 March 2026
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 2, 27 March 2026

11 December 2025

5.8%+1.3 pts

  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 1, 11 December 2025
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 2, 11 December 2025
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 3, 11 December 2025
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 4, 11 December 2025

17 November 2025

4.5%+2.5 pts

  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 1, 17 November 2025
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 2, 17 November 2025
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 3, 17 November 2025
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 4, 17 November 2025

25 June 2025

2.1%+2.1 pts

  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 1, 25 June 2025
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 2, 25 June 2025
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 3, 25 June 2025
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 4, 25 June 2025

29 November 2024

0%

  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 1, 29 November 2024
  • The First Collection At Dubai Studio City construction site, Land Department inspection photo 2, 29 November 2024

All 22 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 51% built on average. The First Collection At Dubai Studio City is behind that average.

Own a unit in The First Collection At Dubai Studio City?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will The First Collection At Dubai Studio City be completed?
The completion date registered with the Dubai Land Department is January 2028. At the pace of its recent inspections the site would reach 100% around August 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The First Collection At Dubai Studio City is built?
21%, measured at the Land Department site inspection on 13 July 2026. The Land Department engineers have inspected the site 6 times since November 2024.
Is The First Collection At Dubai Studio City delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
Who is building The First Collection At Dubai Studio City?
The registered developer is Tfg S C Development.
Which bank holds the escrow account for The First Collection At Dubai Studio City?
Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.