The First Collection At Dubai Studio City construction progress

The registered completion date for The First Collection At Dubai Studio City in Dubai Studio City is January 2028. At the last site inspection, in October 2026, it was 32% built. The developer is Tfg S C Development.

32%

Built, at the site inspection of 12 October 2026

Running behind its date

Registered completion date
January 2028
Finish at recent pace
January 2029
Construction started
February 2025
First registered
February 2025
Developer
Tfg S C Development
Units
589
Escrow bank
Arab Bank
Name in Arabic
ذا فيرست كولكشن ات دبي ستوديو سيتي
Project number
3370
Site inspections
7

Schedule

Between November 2025 and October 2026 the site added about 2.5 points a month. At that rate it would finish around January 2029, more than three months after its registered date of January 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 October 2026

32%+11 pts

  • The First Collection At Dubai Studio City construction site, inspection photo 1, 12 October 2026
  • The First Collection At Dubai Studio City construction site, inspection photo 2, 12 October 2026
  • The First Collection At Dubai Studio City construction site, inspection photo 3, 12 October 2026
  • The First Collection At Dubai Studio City construction site, inspection photo 4, 12 October 2026

13 July 2026

21%+9.2 pts

  • The First Collection At Dubai Studio City construction site, inspection photo 1, 13 July 2026
  • The First Collection At Dubai Studio City construction site, inspection photo 2, 13 July 2026
  • The First Collection At Dubai Studio City construction site, inspection photo 3, 13 July 2026
  • The First Collection At Dubai Studio City construction site, inspection photo 4, 13 July 2026

27 March 2026

12%+6.0 pts

  • The First Collection At Dubai Studio City construction site, inspection photo 1, 27 March 2026
  • The First Collection At Dubai Studio City construction site, inspection photo 2, 27 March 2026

11 December 2025

5.8%+1.3 pts

  • The First Collection At Dubai Studio City construction site, inspection photo 1, 11 December 2025
  • The First Collection At Dubai Studio City construction site, inspection photo 2, 11 December 2025
  • The First Collection At Dubai Studio City construction site, inspection photo 3, 11 December 2025
  • The First Collection At Dubai Studio City construction site, inspection photo 4, 11 December 2025

17 November 2025

4.5%+2.5 pts

  • The First Collection At Dubai Studio City construction site, inspection photo 1, 17 November 2025
  • The First Collection At Dubai Studio City construction site, inspection photo 2, 17 November 2025
  • The First Collection At Dubai Studio City construction site, inspection photo 3, 17 November 2025
  • The First Collection At Dubai Studio City construction site, inspection photo 4, 17 November 2025

25 June 2025

2.1%+2.1 pts

  • The First Collection At Dubai Studio City construction site, inspection photo 1, 25 June 2025
  • The First Collection At Dubai Studio City construction site, inspection photo 2, 25 June 2025
  • The First Collection At Dubai Studio City construction site, inspection photo 3, 25 June 2025
  • The First Collection At Dubai Studio City construction site, inspection photo 4, 25 June 2025

29 November 2024

0%

  • The First Collection At Dubai Studio City construction site, inspection photo 1, 29 November 2024
  • The First Collection At Dubai Studio City construction site, inspection photo 2, 29 November 2024

All 26 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 53% built on average.

Own a unit in The First Collection At Dubai Studio City?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The First Collection At Dubai Studio City handover date?
The registered completion date is January 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The First Collection At Dubai Studio City?
The First Collection At Dubai Studio City was 32% built at the site inspection on 12 October 2026. The site has been inspected 7 times since November 2024. The Land Department took 26 site photos at its inspections.
Is The First Collection At Dubai Studio City delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
Who is building The First Collection At Dubai Studio City?
The registered developer is Tfg S C Development.
Which bank holds the escrow account for The First Collection At Dubai Studio City?
Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.