Ryah Living By Alyakka construction progress

Ryah Living By Alyakka in Dubai Studio City was registered to complete in July 2026 and is still under construction. At the last site inspection, in June 2026, it was 54% built. The developer is Alyakka Developers.

54%

Built, at the site inspection of 1 June 2026

4 months past its registered completion date

Registered completion date
July 2026
Finish at recent pace
August 2027
Construction started
May 2025
First registered
October 2025
Developer
Alyakka Developers
Units
128
Escrow bank
Emirates NBD
Name in Arabic
رياح ليفينغ برعاية ال يكة
Project number
4082
Site inspections
2

Schedule

Ryah Living By Alyakka was registered to complete in July 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around August 2027.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 June 2026

54%+27 pts

  • Ryah Living By Alyakka construction site, inspection photo 1, 1 June 2026
  • Ryah Living By Alyakka construction site, inspection photo 2, 1 June 2026
  • Ryah Living By Alyakka construction site, inspection photo 3, 1 June 2026
  • Ryah Living By Alyakka construction site, inspection photo 4, 1 June 2026

23 September 2025

27%

  • Ryah Living By Alyakka construction site, inspection photo 1, 23 September 2025
  • Ryah Living By Alyakka construction site, inspection photo 2, 23 September 2025
  • Ryah Living By Alyakka construction site, inspection photo 3, 23 September 2025
  • Ryah Living By Alyakka construction site, inspection photo 4, 23 September 2025

All 16 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 53% built on average.

Alyakka Developers has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Ryah Living By Alyakka?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ryah Living By Alyakka handover date?
The registered completion date was July 2026, and the register still lists Ryah Living By Alyakka as under construction. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ryah Living By Alyakka?
Ryah Living By Alyakka was 54% built at the site inspection on 1 June 2026. The site has been inspected 2 times since September 2025. The Land Department took 16 site photos at its inspections.
Is Ryah Living By Alyakka delayed?
Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
Who is building Ryah Living By Alyakka?
The registered developer is Alyakka Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Ryah Living By Alyakka?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.