Ryah Living By Alyakka construction progress

Ryah Living By Alyakka in Dubai Studio City is 54% built at the Land Department inspection of June 2026. Developer Alyakka Developers. Completion registered for July 2026.

54%

Built, at the Land Department site inspection of 1 June 2026

2 months past its registered completion date

Completion date (Land Department)
July 2026
Finish at recent pace
August 2027
Construction started
May 2025
Registered with the Land Department
October 2025
Developer
Alyakka Developers
Units
128
Escrow bank
Emirates NBD
Name in Arabic
رياح ليفينغ برعاية ال يكة
Land Department project number
4082
Land Department site inspections
2

Schedule

Ryah Living By Alyakka was registered to complete in July 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around August 2027.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 June 2026

54%+27 pts

  • Ryah Living By Alyakka construction site, Land Department inspection photo 1, 1 June 2026
  • Ryah Living By Alyakka construction site, Land Department inspection photo 2, 1 June 2026
  • Ryah Living By Alyakka construction site, Land Department inspection photo 3, 1 June 2026
  • Ryah Living By Alyakka construction site, Land Department inspection photo 4, 1 June 2026

23 September 2025

27%

  • Ryah Living By Alyakka construction site, Land Department inspection photo 1, 23 September 2025
  • Ryah Living By Alyakka construction site, Land Department inspection photo 2, 23 September 2025
  • Ryah Living By Alyakka construction site, Land Department inspection photo 3, 23 September 2025
  • Ryah Living By Alyakka construction site, Land Department inspection photo 4, 23 September 2025

All 16 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 51% built on average.

Alyakka Developers has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Ryah Living By Alyakka?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Ryah Living By Alyakka be completed?
The completion date registered with the Dubai Land Department is July 2026. At the pace of its recent inspections the site would reach 100% around August 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Ryah Living By Alyakka is built?
54%, measured at the Land Department site inspection on 1 June 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Ryah Living By Alyakka delayed?
Yes. Its registered completion date of July 2026 has passed and the Land Department still lists it as under construction.
Who is building Ryah Living By Alyakka?
The registered developer is Alyakka Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Ryah Living By Alyakka?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.