Golf Vista Heights construction progress

The register lists Golf Vista Heights in Dubai Sports City as complete. Its last site inspection on record was in May 2026. The developer is London Gate Real Estate Development.

100%

Built, at the site inspection of 12 May 2026

Construction complete

Construction started
August 2023
First registered
January 2024
Units
209
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
جولف فيستا هايتس
Project number
2746
Site inspections
8

Schedule

The register lists Golf Vista Heights as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

12 May 2026

100%+1.3 pts

  • Golf Vista Heights construction site, inspection photo 1, 12 May 2026
  • Golf Vista Heights construction site, inspection photo 2, 12 May 2026
  • Golf Vista Heights construction site, inspection photo 3, 12 May 2026
  • Golf Vista Heights construction site, inspection photo 4, 12 May 2026

23 April 2026

99%+1.3 pts

  • Golf Vista Heights construction site, inspection photo 1, 23 April 2026
  • Golf Vista Heights construction site, inspection photo 2, 23 April 2026
  • Golf Vista Heights construction site, inspection photo 3, 23 April 2026
  • Golf Vista Heights construction site, inspection photo 4, 23 April 2026

2 April 2026

97%+6.8 pts

  • Golf Vista Heights construction site, inspection photo 1, 2 April 2026
  • Golf Vista Heights construction site, inspection photo 2, 2 April 2026
  • Golf Vista Heights construction site, inspection photo 3, 2 April 2026
  • Golf Vista Heights construction site, inspection photo 4, 2 April 2026

24 November 2025

91%+26 pts

  • Golf Vista Heights construction site, inspection photo 1, 24 November 2025
  • Golf Vista Heights construction site, inspection photo 2, 24 November 2025
  • Golf Vista Heights construction site, inspection photo 3, 24 November 2025
  • Golf Vista Heights construction site, inspection photo 4, 24 November 2025

17 June 2025

65%+12 pts

  • Golf Vista Heights construction site, inspection photo 1, 17 June 2025
  • Golf Vista Heights construction site, inspection photo 2, 17 June 2025
  • Golf Vista Heights construction site, inspection photo 3, 17 June 2025
  • Golf Vista Heights construction site, inspection photo 4, 17 June 2025

8 February 2025

53%+12 pts

  • Golf Vista Heights construction site, inspection photo 1, 8 February 2025
  • Golf Vista Heights construction site, inspection photo 2, 8 February 2025
  • Golf Vista Heights construction site, inspection photo 3, 8 February 2025
  • Golf Vista Heights construction site, inspection photo 4, 8 February 2025

2 September 2024

41%+12 pts

  • Golf Vista Heights construction site, inspection photo 1, 2 September 2024
  • Golf Vista Heights construction site, inspection photo 2, 2 September 2024
  • Golf Vista Heights construction site, inspection photo 3, 2 September 2024
  • Golf Vista Heights construction site, inspection photo 4, 2 September 2024

9 November 2023

29%

  • Golf Vista Heights construction site, inspection photo 1, 9 November 2023
  • Golf Vista Heights construction site, inspection photo 2, 9 November 2023
  • Golf Vista Heights construction site, inspection photo 3, 9 November 2023
  • Golf Vista Heights construction site, inspection photo 4, 9 November 2023

All 75 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

London Gate Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Vista Heights?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Golf Vista Heights handover date?
Construction of Golf Vista Heights is recorded as complete. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Golf Vista Heights?
Golf Vista Heights was 100% built at the site inspection on 12 May 2026. The site has been inspected 8 times since November 2023. The Land Department took 75 site photos at its inspections.
Is Golf Vista Heights delayed?
The register lists construction as complete.
Who is building Golf Vista Heights?
The registered developer is London Gate Real Estate Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Vista Heights?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.