Lilian Residences construction progress
The registered completion date for Lilian Residences in Dubai South Residential District is April 2028. At the last site inspection, in October 2026, it was 48% built. The developer is London Gate Real Estate Development.
48%
Built, at the site inspection of 28 October 2026
On pace for its date
- Registered completion date
- April 2028
- Finish at recent pace
- October 2027
- Construction started
- April 2025
- First registered
- May 2025
- Developer
- London Gate Real Estate Development
- Community
- Dubai South Residential District
- Units
- 66
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- مساكن ليليان
- Project number
- 3468
- Site inspections
- 4
Schedule
Since December 2025 Lilian Residences has added about 4.4 points a month. That puts 100% around October 2027, within three months of its registered completion date of April 2028.
Site inspections
28 October 2026
48%+43 pts
6 April 2026
4.7%+4.6 pts
3 December 2025
0.1%+0.1 pts
13 January 2025
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
London Gate Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Lilian Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Lilian Residences handover date?
- The registered completion date is April 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Lilian Residences?
- Lilian Residences was 48% built at the site inspection on 28 October 2026. The site has been inspected 4 times since January 2025. The Land Department took 24 site photos at its inspections.
- Is Lilian Residences delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of April 2028.
- Who is building Lilian Residences?
- The registered developer is London Gate Real Estate Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Lilian Residences?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Aeternitas TowerAlso by London Gate Real Estate Development. 58%, Due December 2027.
- Franck Muller VanguardAlso by London Gate Real Estate Development. 48%, Due November 2027.
- Mi Casa By London Gate Real Estate DevelopmentAlso by London Gate Real Estate Development. 28%, Due October 2028.
- Franck Muller YachtingAlso by London Gate Real Estate Development. 0%, Due July 2028.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.