Skip to content

Franck Muller Vanguard construction progress

The registered completion date for Franck Muller Vanguard in Tecom Site D is November 2027. At the last site inspection, in April 2026, it was 48% built. The developer is London Gate Real Estate Development.

48%

Built, at the site inspection of 30 April 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
May 2028
Construction started
November 2024
First registered
September 2024
Community
Tecom Site D
Units
771
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
فرانك مولر فانغارد
Project number
3202
Site inspections
5

Schedule

Between October 2025 and April 2026 the site added about 2.1 points a month. At that rate it would finish around May 2028, more than three months after its registered date of November 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 April 2026

48%+8.3 pts

  • Franck Muller Vanguard construction site, inspection photo 1, 30 April 2026
  • Franck Muller Vanguard construction site, inspection photo 2, 30 April 2026
  • Franck Muller Vanguard construction site, inspection photo 3, 30 April 2026
  • Franck Muller Vanguard construction site, inspection photo 4, 30 April 2026

20 January 2026

40%+6.5 pts

  • Franck Muller Vanguard construction site, inspection photo 1, 20 January 2026
  • Franck Muller Vanguard construction site, inspection photo 2, 20 January 2026
  • Franck Muller Vanguard construction site, inspection photo 3, 20 January 2026
  • Franck Muller Vanguard construction site, inspection photo 4, 20 January 2026

1 October 2025

34%+5.8 pts

  • Franck Muller Vanguard construction site, inspection photo 1, 1 October 2025
  • Franck Muller Vanguard construction site, inspection photo 2, 1 October 2025
  • Franck Muller Vanguard construction site, inspection photo 3, 1 October 2025
  • Franck Muller Vanguard construction site, inspection photo 4, 1 October 2025

20 March 2025

28%

  • Franck Muller Vanguard construction site, inspection photo 1, 20 March 2025
  • Franck Muller Vanguard construction site, inspection photo 2, 20 March 2025
  • Franck Muller Vanguard construction site, inspection photo 3, 20 March 2025
  • Franck Muller Vanguard construction site, inspection photo 4, 20 March 2025

29 August 2024

28%

  • Franck Muller Vanguard construction site, inspection photo 1, 29 August 2024
  • Franck Muller Vanguard construction site, inspection photo 2, 29 August 2024
  • Franck Muller Vanguard construction site, inspection photo 3, 29 August 2024
  • Franck Muller Vanguard construction site, inspection photo 4, 29 August 2024

All 40 site photos, by inspection date

Context

London Gate Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Franck Muller Vanguard?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Franck Muller Vanguard handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Franck Muller Vanguard?
Franck Muller Vanguard was 48% built at the site inspection on 30 April 2026. The site has been inspected 5 times since August 2024. The Land Department took 40 site photos at its inspections.
Is Franck Muller Vanguard delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Franck Muller Vanguard?
The registered developer is London Gate Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Franck Muller Vanguard?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.