Vincitore Aqua Flora construction progress

Vincitore Aqua Flora in Dubai Science Park is 1.3% built at the Land Department inspection of March 2026. Developer Vincitore Luxury Real Estate Development. Completion registered for June 2028.

1.3%

Built, at the Land Department site inspection of 30 March 2026

Running behind its date

Completion date (Land Department)
June 2028
Finish at recent pace
September 2155
Construction started
January 2025
Registered with the Land Department
September 2024
Developer
Vincitore Luxury Real Estate Development
Units
546
Escrow bank
Mashreq Bank
Name in Arabic
فينسيتور اكوا فلورا
Land Department project number
3154
Land Department site inspections
2

Schedule

Between July 2024 and March 2026 the site added about 0.1 points a month. At that rate it would finish around September 2155, more than three months after the June 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 March 2026

1.3%+1.3 pts

  • Vincitore Aqua Flora construction site, Land Department inspection photo 1, 30 March 2026
  • Vincitore Aqua Flora construction site, Land Department inspection photo 2, 30 March 2026
  • Vincitore Aqua Flora construction site, Land Department inspection photo 3, 30 March 2026
  • Vincitore Aqua Flora construction site, Land Department inspection photo 4, 30 March 2026

25 July 2024

0%

  • Vincitore Aqua Flora construction site, Land Department inspection photo 1, 25 July 2024
  • Vincitore Aqua Flora construction site, Land Department inspection photo 2, 25 July 2024
  • Vincitore Aqua Flora construction site, Land Department inspection photo 3, 25 July 2024

All 8 site photos, by inspection date

Context

Dubai Science Park has 10 projects under construction, 40% built on average.

Own a unit in Vincitore Aqua Flora?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vincitore Aqua Flora be completed?
The completion date registered with the Dubai Land Department is June 2028. At the pace of its recent inspections the site would reach 100% around September 2155. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vincitore Aqua Flora is built?
1.3%, measured at the Land Department site inspection on 30 March 2026. The Land Department engineers have inspected the site 2 times since July 2024.
Is Vincitore Aqua Flora delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Vincitore Aqua Flora?
The registered developer is Vincitore Luxury Real Estate Development.
Which bank holds the escrow account for Vincitore Aqua Flora?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.