Vincitore Aqua Flora construction progress

The registered completion date for Vincitore Aqua Flora in Dubai Science Park is June 2028. At the last site inspection, in March 2026, it was 1.3% built. The developer is Vincitore Luxury Real Estate Development.

1.3%

Built, at the site inspection of 30 March 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
September 2155
Construction started
January 2025
First registered
September 2024
Developer
Vincitore Luxury Real Estate Development
Units
546
Escrow bank
Mashreq Bank
Name in Arabic
فينسيتور اكوا فلورا
Project number
3154
Site inspections
2

Schedule

Between July 2024 and March 2026 the site added about 0.1 points a month. At that rate it would finish around September 2155, more than three months after its registered date of June 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 March 2026

1.3%+1.3 pts

  • Vincitore Aqua Flora construction site, inspection photo 1, 30 March 2026
  • Vincitore Aqua Flora construction site, inspection photo 2, 30 March 2026
  • Vincitore Aqua Flora construction site, inspection photo 3, 30 March 2026
  • Vincitore Aqua Flora construction site, inspection photo 4, 30 March 2026

25 July 2024

0%

  • Vincitore Aqua Flora construction site, inspection photo 1, 25 July 2024
  • Vincitore Aqua Flora construction site, inspection photo 2, 25 July 2024
  • Vincitore Aqua Flora construction site, inspection photo 3, 25 July 2024

All 8 site photos, by inspection date

Context

Dubai Science Park has 10 projects under construction, 43% built on average.

Own a unit in Vincitore Aqua Flora?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Vincitore Aqua Flora handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2155. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Vincitore Aqua Flora?
Vincitore Aqua Flora was 1.3% built at the site inspection on 30 March 2026. The site has been inspected 2 times since July 2024. The Land Department took 8 site photos at its inspections.
Is Vincitore Aqua Flora delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Vincitore Aqua Flora?
The registered developer is Vincitore Luxury Real Estate Development.
Which bank holds the escrow account for Vincitore Aqua Flora?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.