Vincitore Aqua Flora construction progress
The registered completion date for Vincitore Aqua Flora in Dubai Science Park is June 2028. At the last site inspection, in March 2026, it was 1.3% built. The developer is Vincitore Luxury Real Estate Development.
1.3%
Built, at the site inspection of 30 March 2026
Running behind its date
- Registered completion date
- June 2028
- Finish at recent pace
- September 2155
- Construction started
- January 2025
- First registered
- September 2024
- Developer
- Vincitore Luxury Real Estate Development
- Community
- Dubai Science Park
- Units
- 546
- Escrow bank
- Mashreq Bank
- Name in Arabic
- فينسيتور اكوا فلورا
- Project number
- 3154
- Site inspections
- 2
Schedule
Between July 2024 and March 2026 the site added about 0.1 points a month. At that rate it would finish around September 2155, more than three months after its registered date of June 2028.
Site inspections
30 March 2026
1.3%+1.3 pts
25 July 2024
0%
Context
Dubai Science Park has 10 projects under construction, 43% built on average.
Own a unit in Vincitore Aqua Flora?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Vincitore Aqua Flora handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2155. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Vincitore Aqua Flora?
- Vincitore Aqua Flora was 1.3% built at the site inspection on 30 March 2026. The site has been inspected 2 times since July 2024. The Land Department took 8 site photos at its inspections.
- Is Vincitore Aqua Flora delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Vincitore Aqua Flora?
- The registered developer is Vincitore Luxury Real Estate Development.
- Which bank holds the escrow account for Vincitore Aqua Flora?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Vincitore Aqua DimoreNearby in Dubai Science Park. 14%.
- Binghatti HillsNearby in Dubai Science Park. 90%.
- Empire LivingsNearby in Dubai Science Park. 13%, Due November 2027.
- Saas HillsNearby in Dubai Science Park. 17%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)