Empire Livings construction progress
The registered completion date for Empire Livings in Dubai Science Park is November 2027. At the last site inspection, in July 2026, it was 13% built. The developer is Empire Real Estate Developments.
13%
Built, at the site inspection of 31 July 2026
Running behind its date
- Registered completion date
- November 2027
- Finish at recent pace
- August 2031
- Construction started
- November 2024
- First registered
- August 2024
- Developer
- Empire Real Estate Developments
- Community
- Dubai Science Park
- Units
- 210
- Escrow bank
- Emirates NBD
- Name in Arabic
- امباير ليفينجز
- Project number
- 3181
- Site inspections
- 5
Schedule
Between December 2025 and July 2026 the site added about 1.4 points a month. At that rate it would finish around August 2031, more than three months after its registered date of November 2027.
Site inspections
31 July 2026
13%+3.3 pts
22 April 2026
10%+7.9 pts
3 December 2025
2.1%+1.8 pts
11 July 2025
0.4%+0.4 pts
23 July 2024
0%
Context
Dubai Science Park has 10 projects under construction, 43% built on average.
Empire Real Estate Developments has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Empire Livings?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Empire Livings handover date?
- The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Empire Livings?
- Empire Livings was 13% built at the site inspection on 31 July 2026. The site has been inspected 5 times since July 2024. The Land Department took 23 site photos at its inspections.
- Is Empire Livings delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Empire Livings?
- The registered developer is Empire Real Estate Developments. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Empire Livings?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Empire EstatesAlso by Empire Real Estate Developments. 60%, Due December 2026.
- Vincitore Aqua DimoreNearby in Dubai Science Park. 14%.
- Binghatti HillsNearby in Dubai Science Park. 90%.
- Vincitore Aqua FloraNearby in Dubai Science Park. 1.3%, Due June 2028.
- Saas HillsNearby in Dubai Science Park. 17%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

















.jpeg&w=3840&q=75)