Saas Hills construction progress
Saas Hills in Dubai Science Park is 13% built at the Land Department inspection of May 2026. Developer Saas Properties - Dubai Branch. Completion registered for March 2027.
13%
Built, at the Land Department site inspection of 19 May 2026
Running behind its date
- Completion date (Land Department)
- March 2027
- Finish at recent pace
- November 2035
- Construction started
- September 2024
- Registered with the Land Department
- November 2024
- Developer
- Saas Properties - Dubai Branch
- Community
- Dubai Science Park
- Units
- 859
- Escrow bank
- Emirates NBD
- Name in Arabic
- ساس هيلز
- Land Department project number
- 3225
- Land Department site inspections
- 4
Schedule
Between May 2025 and May 2026 the site added about 0.8 points a month. At that rate it would finish around November 2035, more than three months after the March 2027 date registered with the Land Department.
Site inspections
19 May 2026
13%+6.5 pts
10 November 2025
6.4%+2.6 pts
20 May 2025
3.8%+3.8 pts
8 August 2024
0%
Context
Dubai Science Park has 10 projects under construction, 40% built on average.
Own a unit in Saas Hills?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Saas Hills be completed?
- The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around November 2035. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Saas Hills is built?
- 13%, measured at the Land Department site inspection on 19 May 2026. The Land Department engineers have inspected the site 4 times since August 2024.
- Is Saas Hills delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Saas Hills?
- The registered developer is Saas Properties - Dubai Branch.
- Which bank holds the escrow account for Saas Hills?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Vincitore Aqua DimoreNearby in Dubai Science Park. 6.9%.
- Binghatti HillsNearby in Dubai Science Park. 90%.
- Vincitore Aqua FloraNearby in Dubai Science Park. 1.3%, Due June 2028.
- Empire LivingsNearby in Dubai Science Park. 13%, Due November 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.



.jpeg&w=3840&q=75)