Saas Hills construction progress

The registered completion date for Saas Hills in Dubai Science Park is March 2027. At the last site inspection, in November 2026, it was 17% built. The developer is Saas Properties - Dubai Branch.

17%

Built, at the site inspection of 4 November 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
July 2034
Construction started
September 2024
First registered
November 2024
Developer
Saas Properties - Dubai Branch
Units
859
Escrow bank
Emirates NBD
Name in Arabic
ساس هيلز
Project number
3225
Site inspections
5

Schedule

Between November 2025 and November 2026 the site added about 0.9 points a month. At that rate it would finish around July 2034, more than three months after its registered date of March 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 November 2026

17%+4.0 pts

  • Saas Hills construction site, inspection photo 1, 4 November 2026
  • Saas Hills construction site, inspection photo 2, 4 November 2026
  • Saas Hills construction site, inspection photo 3, 4 November 2026
  • Saas Hills construction site, inspection photo 4, 4 November 2026

19 May 2026

13%+6.5 pts

  • Saas Hills construction site, inspection photo 1, 19 May 2026
  • Saas Hills construction site, inspection photo 2, 19 May 2026
  • Saas Hills construction site, inspection photo 3, 19 May 2026
  • Saas Hills construction site, inspection photo 4, 19 May 2026

10 November 2025

6.4%+2.6 pts

  • Saas Hills construction site, inspection photo 1, 10 November 2025
  • Saas Hills construction site, inspection photo 2, 10 November 2025
  • Saas Hills construction site, inspection photo 3, 10 November 2025

20 May 2025

3.8%+3.8 pts

  • Saas Hills construction site, inspection photo 1, 20 May 2025
  • Saas Hills construction site, inspection photo 2, 20 May 2025
  • Saas Hills construction site, inspection photo 3, 20 May 2025
  • Saas Hills construction site, inspection photo 4, 20 May 2025

8 August 2024

0%

  • Saas Hills construction site, inspection photo 1, 8 August 2024
  • Saas Hills construction site, inspection photo 2, 8 August 2024
  • Saas Hills construction site, inspection photo 3, 8 August 2024

All 24 site photos, by inspection date

Context

Dubai Science Park has 10 projects under construction, 43% built on average.

Own a unit in Saas Hills?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Saas Hills handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Saas Hills?
Saas Hills was 17% built at the site inspection on 4 November 2026. The site has been inspected 5 times since August 2024. The Land Department took 24 site photos at its inspections.
Is Saas Hills delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Saas Hills?
The registered developer is Saas Properties - Dubai Branch.
Which bank holds the escrow account for Saas Hills?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.