Samana Ibiza construction progress
Samana Ibiza in Dubai Land Residence Complex is 3.1% built at the Land Department inspection of June 2026. Developer Samana International Real Estate Development. Completion registered for February 2028.
3.1%
Built, at the Land Department site inspection of 18 June 2026
Running behind its date
- Completion date (Land Department)
- February 2028
- Finish at recent pace
- October 2053
- Construction started
- August 2024
- Registered with the Land Department
- September 2024
- Community
- Dubai Land Residence Complex
- Units
- 455
- Escrow bank
- Emirates NBD
- Name in Arabic
- سمانا ايبيزا
- Land Department project number
- 2897
- Land Department site inspections
- 5
Schedule
Between August 2025 and June 2026 the site added about 0.3 points a month. At that rate it would finish around October 2053, more than three months after the February 2028 date registered with the Land Department.
Site inspections
18 June 2026
3.1%+0.7 pts
12 February 2026
2.4%+1.6 pts
24 November 2025
0.8%+0.6 pts
21 August 2025
0.2%+0.2 pts
14 March 2024
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Samana Ibiza?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Samana Ibiza be completed?
- The completion date registered with the Dubai Land Department is February 2028. At the pace of its recent inspections the site would reach 100% around October 2053. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Samana Ibiza is built?
- 3.1%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 5 times since March 2024.
- Is Samana Ibiza delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
- Who is building Samana Ibiza?
- The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Ibiza?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana MykonosAlso by Samana International Real Estate Development. 91%, Due April 2026, passed.
- Samana Mykonos SignatureAlso by Samana International Real Estate Development. 80%, Due April 2026, passed.
- Samana Ivy GardensAlso by Samana International Real Estate Development. 41%.
- Samana Golf ViewsAlso by Samana International Real Estate Development. 56%.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.