Samana Avenue construction progress

The registered completion date for Samana Avenue in Dubai Land Residence Complex is December 2027. At the last site inspection, in October 2026, it was 32% built. The developer is Samana International Real Estate Development.

32%

Built, at the site inspection of 1 October 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
January 2029
Construction started
July 2024
First registered
July 2024
Units
165
Escrow bank
Emirates NBD
Name in Arabic
سامانا افينيو
Project number
2898
Site inspections
6

Schedule

Between October 2025 and October 2026 the site added about 2.5 points a month. At that rate it would finish around January 2029, more than three months after its registered date of December 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 October 2026

32%+10 pts

  • Samana Avenue construction site, inspection photo 1, 1 October 2026
  • Samana Avenue construction site, inspection photo 2, 1 October 2026
  • Samana Avenue construction site, inspection photo 3, 1 October 2026
  • Samana Avenue construction site, inspection photo 4, 1 October 2026

18 June 2026

21%+9.7 pts

  • Samana Avenue construction site, inspection photo 1, 18 June 2026
  • Samana Avenue construction site, inspection photo 2, 18 June 2026
  • Samana Avenue construction site, inspection photo 3, 18 June 2026
  • Samana Avenue construction site, inspection photo 4, 18 June 2026

10 February 2026

12%+8.8 pts

  • Samana Avenue construction site, inspection photo 1, 10 February 2026
  • Samana Avenue construction site, inspection photo 2, 10 February 2026
  • Samana Avenue construction site, inspection photo 3, 10 February 2026
  • Samana Avenue construction site, inspection photo 4, 10 February 2026

16 October 2025

2.9%+1.0 pts

  • Samana Avenue construction site, inspection photo 1, 16 October 2025
  • Samana Avenue construction site, inspection photo 2, 16 October 2025

17 June 2025

1.9%+1.9 pts

  • Samana Avenue construction site, inspection photo 1, 17 June 2025
  • Samana Avenue construction site, inspection photo 2, 17 June 2025
  • Samana Avenue construction site, inspection photo 3, 17 June 2025
  • Samana Avenue construction site, inspection photo 4, 17 June 2025

4 March 2024

0%

  • Samana Avenue construction site, inspection photo 1, 4 March 2024
  • Samana Avenue construction site, inspection photo 2, 4 March 2024
  • Samana Avenue construction site, inspection photo 3, 4 March 2024

All 27 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Samana Avenue?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Avenue handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Samana Avenue?
Samana Avenue was 32% built at the site inspection on 1 October 2026. The site has been inspected 6 times since March 2024. The Land Department took 27 site photos at its inspections.
Is Samana Avenue delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Samana Avenue?
The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Avenue?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.