Samana Avenue construction progress
The registered completion date for Samana Avenue in Dubai Land Residence Complex is December 2027. At the last site inspection, in October 2026, it was 32% built. The developer is Samana International Real Estate Development.
32%
Built, at the site inspection of 1 October 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- January 2029
- Construction started
- July 2024
- First registered
- July 2024
- Community
- Dubai Land Residence Complex
- Units
- 165
- Escrow bank
- Emirates NBD
- Name in Arabic
- سامانا افينيو
- Project number
- 2898
- Site inspections
- 6
Schedule
Between October 2025 and October 2026 the site added about 2.5 points a month. At that rate it would finish around January 2029, more than three months after its registered date of December 2027.
Site inspections
1 October 2026
32%+10 pts
18 June 2026
21%+9.7 pts
10 February 2026
12%+8.8 pts
16 October 2025
2.9%+1.0 pts
17 June 2025
1.9%+1.9 pts
4 March 2024
0%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Samana Avenue?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Avenue handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Samana Avenue?
- Samana Avenue was 32% built at the site inspection on 1 October 2026. The site has been inspected 6 times since March 2024. The Land Department took 27 site photos at its inspections.
- Is Samana Avenue delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Samana Avenue?
- The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Avenue?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana MykonosAlso by Samana International Real Estate Development. 91%, Due April 2026, passed.
- Samana Mykonos SignatureAlso by Samana International Real Estate Development. 86%, Due April 2026, passed.
- Samana Ivy GardensAlso by Samana International Real Estate Development. 41%.
- Samana Golf ViewsAlso by Samana International Real Estate Development. 56%.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)