K1 construction progress

The register lists K1 in Dubai Land Residence Complex as complete, with a registered completion date of November 2021. Its last site inspection on record was in November 2021. The developer is Arabian Gulf Properties.

100%

Built, at the site inspection of 18 November 2021

Construction complete

Registered completion date
November 2021
Construction started
November 2017
First registered
October 2017
Units
144
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
كي 1
Project number
1963
Site inspections
9

Schedule

The register lists K1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 November 2021

100%+1.0 pts

  • K1 construction site, inspection photo 1, 18 November 2021
  • K1 construction site, inspection photo 2, 18 November 2021
  • K1 construction site, inspection photo 3, 18 November 2021
  • K1 construction site, inspection photo 4, 18 November 2021

19 October 2021

99%+4.0 pts

  • K1 construction site, inspection photo 1, 19 October 2021
  • K1 construction site, inspection photo 2, 19 October 2021
  • K1 construction site, inspection photo 3, 19 October 2021
  • K1 construction site, inspection photo 4, 19 October 2021

15 March 2021

95%+15 pts

  • K1 construction site, inspection photo 1, 15 March 2021
  • K1 construction site, inspection photo 2, 15 March 2021
  • K1 construction site, inspection photo 3, 15 March 2021
  • K1 construction site, inspection photo 4, 15 March 2021

4 May 2020

80%+27 pts

  • K1 construction site, inspection photo 1, 4 May 2020
  • K1 construction site, inspection photo 2, 4 May 2020
  • K1 construction site, inspection photo 3, 4 May 2020
  • K1 construction site, inspection photo 4, 4 May 2020

13 October 2019

53%+23 pts

  • K1 construction site, inspection photo 1, 13 October 2019
  • K1 construction site, inspection photo 2, 13 October 2019
  • K1 construction site, inspection photo 3, 13 October 2019
  • K1 construction site, inspection photo 4, 13 October 2019

15 April 2019

30%+19 pts

  • K1 construction site, inspection photo 1, 15 April 2019
  • K1 construction site, inspection photo 2, 15 April 2019
  • K1 construction site, inspection photo 3, 15 April 2019
  • K1 construction site, inspection photo 4, 15 April 2019

26 December 2018

11%+9.2 pts

  • K1 construction site, inspection photo 1, 26 December 2018
  • K1 construction site, inspection photo 2, 26 December 2018
  • K1 construction site, inspection photo 3, 26 December 2018
  • K1 construction site, inspection photo 4, 26 December 2018

22 July 2018

2.1%+1.9 pts

  • K1 construction site, inspection photo 1, 22 July 2018
  • K1 construction site, inspection photo 2, 22 July 2018
  • K1 construction site, inspection photo 3, 22 July 2018
  • K1 construction site, inspection photo 4, 22 July 2018

18 March 2018

0.2%

  • K1 construction site, inspection photo 1, 18 March 2018
  • K1 construction site, inspection photo 2, 18 March 2018
  • K1 construction site, inspection photo 3, 18 March 2018
  • K1 construction site, inspection photo 4, 18 March 2018

All 83 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Arabian Gulf Properties has 3 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in K1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the K1 handover date?
Construction of K1 is recorded as complete, with a registered completion date of November 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on K1?
K1 was 100% built at the site inspection on 18 November 2021. The site has been inspected 9 times since March 2018. The Land Department took 83 site photos at its inspections.
Is K1 delayed?
The register lists construction as complete.
Who is building K1?
The registered developer is Arabian Gulf Properties. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for K1?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.