The Corner construction progress

The Corner in Dubai Land Residence Complex is 38% built at the Land Department inspection of June 2026. Developer Arabian Gulf Properties. Completion registered for June 2027.

38%

Built, at the Land Department site inspection of 1 June 2026

Running behind its date

Completion date (Land Department)
June 2027
Finish at recent pace
February 2030
Construction started
September 2024
Registered with the Land Department
June 2025
Units
126
Escrow bank
Mashreq Bank
Name in Arabic
ذا كورنر
Land Department project number
2904
Land Department site inspections
5

Schedule

Between September 2025 and June 2026 the site added about 1.4 points a month. At that rate it would finish around February 2030, more than three months after the June 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 June 2026

38%+3.9 pts

  • The Corner construction site, Land Department inspection photo 1, 1 June 2026
  • The Corner construction site, Land Department inspection photo 2, 1 June 2026
  • The Corner construction site, Land Department inspection photo 3, 1 June 2026
  • The Corner construction site, Land Department inspection photo 4, 1 June 2026

6 February 2026

34%+8.4 pts

  • The Corner construction site, Land Department inspection photo 1, 6 February 2026
  • The Corner construction site, Land Department inspection photo 2, 6 February 2026
  • The Corner construction site, Land Department inspection photo 3, 6 February 2026
  • The Corner construction site, Land Department inspection photo 4, 6 February 2026

8 September 2025

25%+8.1 pts

  • The Corner construction site, Land Department inspection photo 1, 8 September 2025
  • The Corner construction site, Land Department inspection photo 2, 8 September 2025
  • The Corner construction site, Land Department inspection photo 3, 8 September 2025
  • The Corner construction site, Land Department inspection photo 4, 8 September 2025

20 May 2025

17%+15 pts

  • The Corner construction site, Land Department inspection photo 1, 20 May 2025
  • The Corner construction site, Land Department inspection photo 2, 20 May 2025
  • The Corner construction site, Land Department inspection photo 3, 20 May 2025
  • The Corner construction site, Land Department inspection photo 4, 20 May 2025

10 December 2024

2.2%

  • The Corner construction site, Land Department inspection photo 1, 10 December 2024
  • The Corner construction site, Land Department inspection photo 2, 10 December 2024
  • The Corner construction site, Land Department inspection photo 3, 10 December 2024
  • The Corner construction site, Land Department inspection photo 4, 10 December 2024

All 33 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

Arabian Gulf Properties has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The Corner?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Corner be completed?
The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around February 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Corner is built?
38%, measured at the Land Department site inspection on 1 June 2026. The Land Department engineers have inspected the site 5 times since December 2024.
Is The Corner delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building The Corner?
The registered developer is Arabian Gulf Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for The Corner?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.