A 99 construction progress
A 99 in Dubai Land Residence Complex is 45% built at the Land Department inspection of July 2026. Developer Arabian Gulf Properties. Completion registered for October 2026.
45%
Built, at the Land Department site inspection of 1 July 2026
Running behind its date
- Completion date (Land Department)
- October 2026
- Finish at recent pace
- November 2033
- Construction started
- October 2023
- Registered with the Land Department
- September 2024
- Developer
- Arabian Gulf Properties
- Community
- Dubai Land Residence Complex
- Units
- 90
- Escrow bank
- United Bank Limited
- Name in Arabic
- أيه 99
- Land Department project number
- 2768
- Land Department site inspections
- 6
Schedule
Between October 2025 and July 2026 the site added about 0.6 points a month. At that rate it would finish around November 2033, more than three months after the October 2026 date registered with the Land Department.
Site inspections
1 July 2026
45%+2.8 pts
8 April 2026
42%+2.5 pts
10 October 2025
40%+5.2 pts
12 June 2025
35%+14 pts
20 December 2024
21%+21 pts
1 May 2024
0.3%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Arabian Gulf Properties has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in A 99?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will A 99 be completed?
- The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around November 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of A 99 is built?
- 45%, measured at the Land Department site inspection on 1 July 2026. The Land Department engineers have inspected the site 6 times since May 2024.
- Is A 99 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2026.
- Who is building A 99?
- The registered developer is Arabian Gulf Properties. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for A 99?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Parkwood ResidencesAlso by Arabian Gulf Properties. 57%, Due April 2026, passed.
- The CornerAlso by Arabian Gulf Properties. 38%, Due June 2027.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)