Skip to content

A 99 construction progress

A 99 in Dubai Land Residence Complex is 45% built at the Land Department inspection of July 2026. Developer Arabian Gulf Properties. Completion registered for October 2026.

45%

Built, at the Land Department site inspection of 1 July 2026

Running behind its date

Completion date (Land Department)
October 2026
Finish at recent pace
November 2033
Construction started
October 2023
Registered with the Land Department
September 2024
Units
90
Escrow bank
United Bank Limited
Name in Arabic
أيه 99
Land Department project number
2768
Land Department site inspections
6

Schedule

Between October 2025 and July 2026 the site added about 0.6 points a month. At that rate it would finish around November 2033, more than three months after the October 2026 date registered with the Land Department.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 July 2026

45%+2.8 pts

  • A 99 construction site, Land Department inspection photo 1, 1 July 2026
  • A 99 construction site, Land Department inspection photo 2, 1 July 2026
  • A 99 construction site, Land Department inspection photo 3, 1 July 2026
  • A 99 construction site, Land Department inspection photo 4, 1 July 2026

8 April 2026

42%+2.5 pts

  • A 99 construction site, Land Department inspection photo 1, 8 April 2026
  • A 99 construction site, Land Department inspection photo 2, 8 April 2026
  • A 99 construction site, Land Department inspection photo 3, 8 April 2026
  • A 99 construction site, Land Department inspection photo 4, 8 April 2026

10 October 2025

40%+5.2 pts

  • A 99 construction site, Land Department inspection photo 1, 10 October 2025
  • A 99 construction site, Land Department inspection photo 2, 10 October 2025
  • A 99 construction site, Land Department inspection photo 3, 10 October 2025
  • A 99 construction site, Land Department inspection photo 4, 10 October 2025

12 June 2025

35%+14 pts

  • A 99 construction site, Land Department inspection photo 1, 12 June 2025
  • A 99 construction site, Land Department inspection photo 2, 12 June 2025
  • A 99 construction site, Land Department inspection photo 3, 12 June 2025
  • A 99 construction site, Land Department inspection photo 4, 12 June 2025

20 December 2024

21%+21 pts

  • A 99 construction site, Land Department inspection photo 1, 20 December 2024
  • A 99 construction site, Land Department inspection photo 2, 20 December 2024
  • A 99 construction site, Land Department inspection photo 3, 20 December 2024
  • A 99 construction site, Land Department inspection photo 4, 20 December 2024

1 May 2024

0.3%

  • A 99 construction site, Land Department inspection photo 1, 1 May 2024
  • A 99 construction site, Land Department inspection photo 2, 1 May 2024

All 36 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

Arabian Gulf Properties has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in A 99?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will A 99 be completed?
The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around November 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of A 99 is built?
45%, measured at the Land Department site inspection on 1 July 2026. The Land Department engineers have inspected the site 6 times since May 2024.
Is A 99 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2026.
Who is building A 99?
The registered developer is Arabian Gulf Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for A 99?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.