A 99 construction progress
A 99 in Dubai Land Residence Complex was registered to complete in October 2026 and is still under construction. At the last site inspection, in October 2026, it was 48% built. The developer is Arabian Gulf Properties.
48%
Built, at the site inspection of 19 October 2026
1 months past its registered completion date
- Registered completion date
- October 2026
- Finish at recent pace
- November 2031
- Construction started
- October 2023
- First registered
- September 2024
- Developer
- Arabian Gulf Properties
- Community
- Dubai Land Residence Complex
- Units
- 90
- Escrow bank
- United Bank Limited
- Name in Arabic
- أيه 99
- Project number
- 2768
- Site inspections
- 7
Schedule
A 99 was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 0.9 points a month. Kept at that rate, the site would reach 100% around November 2031.
Site inspections
19 October 2026
48%+2.7 pts
1 July 2026
45%+2.8 pts
8 April 2026
42%+2.5 pts
10 October 2025
40%+5.2 pts
12 June 2025
35%+14 pts
20 December 2024
21%+21 pts
1 May 2024
0.3%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Arabian Gulf Properties has 3 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in A 99?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the A 99 handover date?
- The registered completion date was October 2026, and the register still lists A 99 as under construction. At the pace of its recent inspections the site would reach 100% around November 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on A 99?
- A 99 was 48% built at the site inspection on 19 October 2026. The site has been inspected 7 times since May 2024. The Land Department took 44 site photos at its inspections.
- Is A 99 delayed?
- Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
- Who is building A 99?
- The registered developer is Arabian Gulf Properties. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for A 99?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Parkwood ResidencesAlso by Arabian Gulf Properties. 57%, Due April 2026, passed.
- The CornerAlso by Arabian Gulf Properties. 38%, Due June 2027.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)