A 99 construction progress

A 99 in Dubai Land Residence Complex was registered to complete in October 2026 and is still under construction. At the last site inspection, in October 2026, it was 48% built. The developer is Arabian Gulf Properties.

48%

Built, at the site inspection of 19 October 2026

1 months past its registered completion date

Registered completion date
October 2026
Finish at recent pace
November 2031
Construction started
October 2023
First registered
September 2024
Units
90
Escrow bank
United Bank Limited
Name in Arabic
أيه 99
Project number
2768
Site inspections
7

Schedule

A 99 was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 0.9 points a month. Kept at that rate, the site would reach 100% around November 2031.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 October 2026

48%+2.7 pts

  • A 99 construction site, inspection photo 1, 19 October 2026
  • A 99 construction site, inspection photo 2, 19 October 2026
  • A 99 construction site, inspection photo 3, 19 October 2026
  • A 99 construction site, inspection photo 4, 19 October 2026

1 July 2026

45%+2.8 pts

  • A 99 construction site, inspection photo 1, 1 July 2026
  • A 99 construction site, inspection photo 2, 1 July 2026
  • A 99 construction site, inspection photo 3, 1 July 2026
  • A 99 construction site, inspection photo 4, 1 July 2026

8 April 2026

42%+2.5 pts

  • A 99 construction site, inspection photo 1, 8 April 2026
  • A 99 construction site, inspection photo 2, 8 April 2026
  • A 99 construction site, inspection photo 3, 8 April 2026
  • A 99 construction site, inspection photo 4, 8 April 2026

10 October 2025

40%+5.2 pts

  • A 99 construction site, inspection photo 1, 10 October 2025
  • A 99 construction site, inspection photo 2, 10 October 2025
  • A 99 construction site, inspection photo 3, 10 October 2025
  • A 99 construction site, inspection photo 4, 10 October 2025

12 June 2025

35%+14 pts

  • A 99 construction site, inspection photo 1, 12 June 2025
  • A 99 construction site, inspection photo 2, 12 June 2025
  • A 99 construction site, inspection photo 3, 12 June 2025
  • A 99 construction site, inspection photo 4, 12 June 2025

20 December 2024

21%+21 pts

  • A 99 construction site, inspection photo 1, 20 December 2024
  • A 99 construction site, inspection photo 2, 20 December 2024
  • A 99 construction site, inspection photo 3, 20 December 2024
  • A 99 construction site, inspection photo 4, 20 December 2024

1 May 2024

0.3%

  • A 99 construction site, inspection photo 1, 1 May 2024
  • A 99 construction site, inspection photo 2, 1 May 2024

All 44 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Arabian Gulf Properties has 3 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in A 99?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the A 99 handover date?
The registered completion date was October 2026, and the register still lists A 99 as under construction. At the pace of its recent inspections the site would reach 100% around November 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on A 99?
A 99 was 48% built at the site inspection on 19 October 2026. The site has been inspected 7 times since May 2024. The Land Department took 44 site photos at its inspections.
Is A 99 delayed?
Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
Who is building A 99?
The registered developer is Arabian Gulf Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for A 99?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.