K1 construction photos
83 photos from 9 site inspections, newest first. The percentage is how much of K1 was built on the day of each visit.
18 November 2021100% built
19 October 202199% built
15 March 202195% built
4 May 202080% built
13 October 201953% built
15 April 201930% built
26 December 201811% built
22 July 20182.1% built
18 March 20180.2% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.