Skip to content

Parkwood Residences construction progress

Parkwood Residences in Jumeirah Village Circle was registered to complete in April 2026 and is still under construction. At the last site inspection, in September 2026, it was 57% built. The developer is Arabian Gulf Properties.

57%

Built, at the site inspection of 18 September 2026

7 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
December 2029
Construction started
December 2023
First registered
June 2024
Units
174
Escrow bank
Mashreq Bank
Name in Arabic
باركوود ريزيدنسز
Project number
2764
Site inspections
9

Schedule

Parkwood Residences was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 1.1 points a month. Kept at that rate, the site would reach 100% around December 2029.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 September 2026

57%+5.0 pts

  • Parkwood Residences construction site, inspection photo 1, 18 September 2026
  • Parkwood Residences construction site, inspection photo 2, 18 September 2026
  • Parkwood Residences construction site, inspection photo 3, 18 September 2026
  • Parkwood Residences construction site, inspection photo 4, 18 September 2026

1 June 2026

52%+4.0 pts

  • Parkwood Residences construction site, inspection photo 1, 1 June 2026
  • Parkwood Residences construction site, inspection photo 2, 1 June 2026
  • Parkwood Residences construction site, inspection photo 3, 1 June 2026
  • Parkwood Residences construction site, inspection photo 4, 1 June 2026

5 February 2026

48%+1.6 pts

  • Parkwood Residences construction site, inspection photo 1, 5 February 2026
  • Parkwood Residences construction site, inspection photo 2, 5 February 2026
  • Parkwood Residences construction site, inspection photo 3, 5 February 2026
  • Parkwood Residences construction site, inspection photo 4, 5 February 2026

4 December 2025

46%+5.1 pts

  • Parkwood Residences construction site, inspection photo 1, 4 December 2025
  • Parkwood Residences construction site, inspection photo 2, 4 December 2025
  • Parkwood Residences construction site, inspection photo 3, 4 December 2025
  • Parkwood Residences construction site, inspection photo 4, 4 December 2025

1 August 2025

41%+1.3 pts

  • Parkwood Residences construction site, inspection photo 1, 1 August 2025
  • Parkwood Residences construction site, inspection photo 2, 1 August 2025
  • Parkwood Residences construction site, inspection photo 3, 1 August 2025
  • Parkwood Residences construction site, inspection photo 4, 1 August 2025

26 June 2025

40%+8.0 pts

  • Parkwood Residences construction site, inspection photo 1, 26 June 2025
  • Parkwood Residences construction site, inspection photo 2, 26 June 2025
  • Parkwood Residences construction site, inspection photo 3, 26 June 2025
  • Parkwood Residences construction site, inspection photo 4, 26 June 2025

17 January 2025

32%+3.5 pts

  • Parkwood Residences construction site, inspection photo 1, 17 January 2025
  • Parkwood Residences construction site, inspection photo 2, 17 January 2025
  • Parkwood Residences construction site, inspection photo 3, 17 January 2025
  • Parkwood Residences construction site, inspection photo 4, 17 January 2025

16 September 2024

29%+14 pts

  • Parkwood Residences construction site, inspection photo 1, 16 September 2024
  • Parkwood Residences construction site, inspection photo 2, 16 September 2024
  • Parkwood Residences construction site, inspection photo 3, 16 September 2024
  • Parkwood Residences construction site, inspection photo 4, 16 September 2024

20 March 2024

15%

  • Parkwood Residences construction site, inspection photo 1, 20 March 2024
  • Parkwood Residences construction site, inspection photo 2, 20 March 2024
  • Parkwood Residences construction site, inspection photo 3, 20 March 2024
  • Parkwood Residences construction site, inspection photo 4, 20 March 2024

All 61 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Arabian Gulf Properties has 3 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Parkwood Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Parkwood Residences handover date?
The registered completion date was April 2026, and the register still lists Parkwood Residences as under construction. At the pace of its recent inspections the site would reach 100% around December 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Parkwood Residences?
Parkwood Residences was 57% built at the site inspection on 18 September 2026. The site has been inspected 9 times since March 2024. The Land Department took 61 site photos at its inspections.
Is Parkwood Residences delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Parkwood Residences?
The registered developer is Arabian Gulf Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Parkwood Residences?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.