Parkwood Residences construction progress

Parkwood Residences in Jumeirah Village Circle is 57% built at the Land Department inspection of September 2026. Developer Arabian Gulf Properties. Completion registered for April 2026.

57%

Built, at the Land Department site inspection of 18 September 2026

5 months past its registered completion date

Completion date (Land Department)
April 2026
Finish at recent pace
December 2029
Construction started
December 2023
Registered with the Land Department
June 2024
Units
174
Escrow bank
Mashreq Bank
Name in Arabic
باركوود ريزيدنسز
Land Department project number
2764
Land Department site inspections
9

Schedule

Parkwood Residences was registered to complete in April 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 1.1 points a month. Kept at that rate, the site would reach 100% around December 2029.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 September 2026

57%+5.0 pts

  • Parkwood Residences construction site, Land Department inspection photo 1, 18 September 2026
  • Parkwood Residences construction site, Land Department inspection photo 2, 18 September 2026
  • Parkwood Residences construction site, Land Department inspection photo 3, 18 September 2026
  • Parkwood Residences construction site, Land Department inspection photo 4, 18 September 2026

1 June 2026

52%+4.0 pts

  • Parkwood Residences construction site, Land Department inspection photo 1, 1 June 2026
  • Parkwood Residences construction site, Land Department inspection photo 2, 1 June 2026
  • Parkwood Residences construction site, Land Department inspection photo 3, 1 June 2026
  • Parkwood Residences construction site, Land Department inspection photo 4, 1 June 2026

5 February 2026

48%+1.6 pts

  • Parkwood Residences construction site, Land Department inspection photo 1, 5 February 2026
  • Parkwood Residences construction site, Land Department inspection photo 2, 5 February 2026
  • Parkwood Residences construction site, Land Department inspection photo 3, 5 February 2026
  • Parkwood Residences construction site, Land Department inspection photo 4, 5 February 2026

4 December 2025

46%+5.1 pts

  • Parkwood Residences construction site, Land Department inspection photo 1, 4 December 2025
  • Parkwood Residences construction site, Land Department inspection photo 2, 4 December 2025
  • Parkwood Residences construction site, Land Department inspection photo 3, 4 December 2025
  • Parkwood Residences construction site, Land Department inspection photo 4, 4 December 2025

1 August 2025

41%+1.3 pts

  • Parkwood Residences construction site, Land Department inspection photo 1, 1 August 2025
  • Parkwood Residences construction site, Land Department inspection photo 2, 1 August 2025
  • Parkwood Residences construction site, Land Department inspection photo 3, 1 August 2025
  • Parkwood Residences construction site, Land Department inspection photo 4, 1 August 2025

26 June 2025

40%+8.0 pts

  • Parkwood Residences construction site, Land Department inspection photo 1, 26 June 2025
  • Parkwood Residences construction site, Land Department inspection photo 2, 26 June 2025
  • Parkwood Residences construction site, Land Department inspection photo 3, 26 June 2025
  • Parkwood Residences construction site, Land Department inspection photo 4, 26 June 2025

17 January 2025

32%+3.5 pts

  • Parkwood Residences construction site, Land Department inspection photo 1, 17 January 2025
  • Parkwood Residences construction site, Land Department inspection photo 2, 17 January 2025
  • Parkwood Residences construction site, Land Department inspection photo 3, 17 January 2025
  • Parkwood Residences construction site, Land Department inspection photo 4, 17 January 2025

16 September 2024

29%+14 pts

  • Parkwood Residences construction site, Land Department inspection photo 1, 16 September 2024
  • Parkwood Residences construction site, Land Department inspection photo 2, 16 September 2024
  • Parkwood Residences construction site, Land Department inspection photo 3, 16 September 2024
  • Parkwood Residences construction site, Land Department inspection photo 4, 16 September 2024

20 March 2024

15%

  • Parkwood Residences construction site, Land Department inspection photo 1, 20 March 2024
  • Parkwood Residences construction site, Land Department inspection photo 2, 20 March 2024
  • Parkwood Residences construction site, Land Department inspection photo 3, 20 March 2024
  • Parkwood Residences construction site, Land Department inspection photo 4, 20 March 2024

All 61 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Arabian Gulf Properties has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Parkwood Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Parkwood Residences be completed?
The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around December 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Parkwood Residences is built?
57%, measured at the Land Department site inspection on 18 September 2026. The Land Department engineers have inspected the site 9 times since March 2024.
Is Parkwood Residences delayed?
Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
Who is building Parkwood Residences?
The registered developer is Arabian Gulf Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Parkwood Residences?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.