Floarea Oasis construction progress
Floarea Oasis in Dubai Land Residence Complex is 13% built at the Land Department inspection of September 2026. Developer Mashriq Elite Real Estate Development. Completion registered for December 2028.
13%
Built, at the Land Department site inspection of 15 September 2026
Running behind its date
- Completion date (Land Department)
- December 2028
- Finish at recent pace
- November 2032
- Construction started
- July 2025
- Registered with the Land Department
- April 2025
- Community
- Dubai Land Residence Complex
- Units
- 257
- Escrow bank
- Mashreq Bank
- Name in Arabic
- فلوريا أو أسس
- Land Department project number
- 3603
- Land Department site inspections
- 5
Schedule
Between October 2025 and September 2026 the site added about 1.2 points a month. At that rate it would finish around November 2032, more than three months after the December 2028 date registered with the Land Department.
Site inspections
15 September 2026
13%+8.9 pts
5 May 2026
3.7%+1.5 pts
4 February 2026
2.2%+2.0 pts
30 October 2025
0.2%+0.2 pts
2 April 2025
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Mashriq Elite Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Floarea Oasis?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Floarea Oasis be completed?
- The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around November 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Floarea Oasis is built?
- 13%, measured at the Land Department site inspection on 15 September 2026. The Land Department engineers have inspected the site 5 times since April 2025.
- Is Floarea Oasis delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Floarea Oasis?
- The registered developer is Mashriq Elite Real Estate Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Floarea Oasis?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Floarea VistaAlso by Mashriq Elite Real Estate Development. 63%.
- Floarea GrandeAlso by Mashriq Elite Real Estate Development. 48%, Due August 2027.
- Floarea SkiesAlso by Mashriq Elite Real Estate Development. 4.5%, Due December 2028.
- Floarea BreezeAlso by Mashriq Elite Real Estate Development. 0%, Due June 2028.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)







.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)