Floarea Breeze construction progress

The registered completion date for Floarea Breeze in Palm Deira is June 2028. At the last site inspection, in October 2026, it was 3.8% built. The developer is Mashriq Elite Real Estate Development.

3.8%

Built, at the site inspection of 26 October 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
October 2055
Construction started
January 2026
First registered
November 2025
Community
Palm Deira
Units
52
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
فلوريا نسيم
Project number
4061
Site inspections
2

Schedule

Between September 2025 and October 2026 the site added about 0.3 points a month. At that rate it would finish around October 2055, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 October 2026

3.8%+3.8 pts

  • Floarea Breeze construction site, inspection photo 1, 26 October 2026
  • Floarea Breeze construction site, inspection photo 2, 26 October 2026
  • Floarea Breeze construction site, inspection photo 3, 26 October 2026
  • Floarea Breeze construction site, inspection photo 4, 26 October 2026

2 September 2025

0%

  • Floarea Breeze construction site, inspection photo 1, 2 September 2025
  • Floarea Breeze construction site, inspection photo 2, 2 September 2025

All 7 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Mashriq Elite Real Estate Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Floarea Breeze?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Floarea Breeze handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2055. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Floarea Breeze?
Floarea Breeze was 3.8% built at the site inspection on 26 October 2026. The site has been inspected 2 times since September 2025. The Land Department took 7 site photos at its inspections.
Is Floarea Breeze delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Floarea Breeze?
The registered developer is Mashriq Elite Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Floarea Breeze?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.