Floarea Breeze construction progress
The registered completion date for Floarea Breeze in Palm Deira is June 2028. At the last site inspection, in October 2026, it was 3.8% built. The developer is Mashriq Elite Real Estate Development.
3.8%
Built, at the site inspection of 26 October 2026
Running behind its date
- Registered completion date
- June 2028
- Finish at recent pace
- October 2055
- Construction started
- January 2026
- First registered
- November 2025
- Community
- Palm Deira
- Units
- 52
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- فلوريا نسيم
- Project number
- 4061
- Site inspections
- 2
Schedule
Between September 2025 and October 2026 the site added about 0.3 points a month. At that rate it would finish around October 2055, more than three months after its registered date of June 2028.
Site inspections
26 October 2026
3.8%+3.8 pts
2 September 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Mashriq Elite Real Estate Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Floarea Breeze?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Floarea Breeze handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2055. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Floarea Breeze?
- Floarea Breeze was 3.8% built at the site inspection on 26 October 2026. The site has been inspected 2 times since September 2025. The Land Department took 7 site photos at its inspections.
- Is Floarea Breeze delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Floarea Breeze?
- The registered developer is Mashriq Elite Real Estate Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Floarea Breeze?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Floarea VistaAlso by Mashriq Elite Real Estate Development. 63%, Due June 2026, passed.
- Floarea GrandeAlso by Mashriq Elite Real Estate Development. 48%, Due August 2027.
- Floarea OasisAlso by Mashriq Elite Real Estate Development. 13%, Due December 2028.
- Floarea SkiesAlso by Mashriq Elite Real Estate Development. 4.5%, Due December 2028.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.