Floarea Oasis construction photos

18 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of Floarea Oasis was built on the day of each visit.

15 September 202613% built

5 May 20263.7% built

4 February 20262.2% built

30 October 20250.2% built

2 April 20250% built

Back to Floarea Oasis construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.