Floarea Skies construction progress
The registered completion date for Floarea Skies in Jumeirah Village Circle is December 2028. At the last site inspection, in July 2026, it was 4.5% built. The developer is Mashriq Elite Real Estate Development.
4.5%
Built, at the site inspection of 6 July 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- March 2040
- Construction started
- August 2025
- First registered
- June 2025
- Community
- Jumeirah Village Circle
- Units
- 195
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- فلوريا السماء
- Project number
- 3717
- Site inspections
- 3
Schedule
Between November 2025 and July 2026 the site added about 0.6 points a month. At that rate it would finish around March 2040, more than three months after its registered date of December 2028.
Site inspections
6 July 2026
4.5%+4.5 pts
12 November 2025
0%+0.0 pts
6 May 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Mashriq Elite Real Estate Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Floarea Skies?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Floarea Skies handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2040. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Floarea Skies?
- Floarea Skies was 4.5% built at the site inspection on 6 July 2026. The site has been inspected 3 times since May 2025. The Land Department took 7 site photos at its inspections.
- Is Floarea Skies delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Floarea Skies?
- The registered developer is Mashriq Elite Real Estate Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Floarea Skies?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Floarea VistaAlso by Mashriq Elite Real Estate Development. 63%, Due June 2026, passed.
- Floarea GrandeAlso by Mashriq Elite Real Estate Development. 48%, Due August 2027.
- Floarea OasisAlso by Mashriq Elite Real Estate Development. 13%, Due December 2028.
- Floarea BreezeAlso by Mashriq Elite Real Estate Development. 3.8%, Due June 2028.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.