Floarea Skies construction progress

The registered completion date for Floarea Skies in Jumeirah Village Circle is December 2028. At the last site inspection, in July 2026, it was 4.5% built. The developer is Mashriq Elite Real Estate Development.

4.5%

Built, at the site inspection of 6 July 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
March 2040
Construction started
August 2025
First registered
June 2025
Units
195
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
فلوريا السماء
Project number
3717
Site inspections
3

Schedule

Between November 2025 and July 2026 the site added about 0.6 points a month. At that rate it would finish around March 2040, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 July 2026

4.5%+4.5 pts

  • Floarea Skies construction site, inspection photo 1, 6 July 2026
  • Floarea Skies construction site, inspection photo 2, 6 July 2026
  • Floarea Skies construction site, inspection photo 3, 6 July 2026

12 November 2025

0%+0.0 pts

  • Floarea Skies construction site, inspection photo 1, 12 November 2025
  • Floarea Skies construction site, inspection photo 2, 12 November 2025

6 May 2025

0%

  • Floarea Skies construction site, inspection photo 1, 6 May 2025
  • Floarea Skies construction site, inspection photo 2, 6 May 2025

All 7 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Mashriq Elite Real Estate Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Floarea Skies?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Floarea Skies handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2040. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Floarea Skies?
Floarea Skies was 4.5% built at the site inspection on 6 July 2026. The site has been inspected 3 times since May 2025. The Land Department took 7 site photos at its inspections.
Is Floarea Skies delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Floarea Skies?
The registered developer is Mashriq Elite Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Floarea Skies?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.