Cove Edition Residence 5 By Imtiaz construction progress

Cove Edition Residence 5 By Imtiaz in Dubai Land Residence Complex is 26% built at the Land Department inspection of August 2026. Developer Imtiaz Real Estate Investment & Development. Completion registered for May 2027.

26%

Built, at the Land Department site inspection of 18 August 2026

Running behind its date

Completion date (Land Department)
May 2027
Finish at recent pace
April 2029
Construction started
May 2025
Registered with the Land Department
May 2025
Units
198
Escrow bank
Dubai Islamic Bank
Name in Arabic
كوف ايديشن ريزيدنس 5 من امتياز
Land Department project number
3705
Land Department site inspections
6

Schedule

Between September 2025 and August 2026 the site added about 2.3 points a month. At that rate it would finish around April 2029, more than three months after the May 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 August 2026

26%+10 pts

  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 1, 18 August 2026
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 2, 18 August 2026
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 3, 18 August 2026
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 4, 18 August 2026

3 June 2026

16%+6.9 pts

  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 1, 3 June 2026
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 2, 3 June 2026
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 3, 3 June 2026
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 4, 3 June 2026

26 February 2026

9.1%+5.5 pts

  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 1, 26 February 2026
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 2, 26 February 2026
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 3, 26 February 2026
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 4, 26 February 2026

3 December 2025

3.7%+2.0 pts

  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 1, 3 December 2025
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 2, 3 December 2025
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 3, 3 December 2025

26 September 2025

1.7%+1.7 pts

  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 1, 26 September 2025
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 2, 26 September 2025
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 3, 26 September 2025
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 4, 26 September 2025

28 April 2025

0%

  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 1, 28 April 2025
  • Cove Edition Residence 5 By Imtiaz construction site, Land Department inspection photo 2, 28 April 2025

All 36 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

Imtiaz Real Estate Investment & Development has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Cove Edition Residence 5 By Imtiaz?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Cove Edition Residence 5 By Imtiaz be completed?
The completion date registered with the Dubai Land Department is May 2027. At the pace of its recent inspections the site would reach 100% around April 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Cove Edition Residence 5 By Imtiaz is built?
26%, measured at the Land Department site inspection on 18 August 2026. The Land Department engineers have inspected the site 6 times since April 2025.
Is Cove Edition Residence 5 By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Cove Edition Residence 5 By Imtiaz?
The registered developer is Imtiaz Real Estate Investment & Development. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Cove Edition Residence 5 By Imtiaz?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.