Cove Edition Residence 5 By Imtiaz construction photos

46 photos from 7 site inspections, newest first. The percentage is how much of Cove Edition Residence 5 By Imtiaz was built on the day of each visit.

16 November 202641% built

18 August 202626% built

3 June 202616% built

26 February 20269.1% built

3 December 20253.7% built

26 September 20251.7% built

28 April 20250% built

Back to Cove Edition Residence 5 By Imtiaz construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.