Cove Edition Residence 2 By Imtiaz construction progress

Cove Edition Residence 2 By Imtiaz in Dubai Land Residence Complex was registered to complete in October 2026 and is still under construction. At the last site inspection, in October 2026, it was 60% built. The developer is Imtiaz Real Estate Investment & Development.

60%

Built, at the site inspection of 20 October 2026

1 months past its registered completion date

Registered completion date
October 2026
Finish at recent pace
July 2027
Construction started
October 2024
First registered
October 2024
Units
260
Escrow bank
Dubai Islamic Bank
Name in Arabic
كوف ايديشن ريزيدنس 2 من امتياز
Project number
3286
Site inspections
8

Schedule

Cove Edition Residence 2 By Imtiaz was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 4.6 points a month. Kept at that rate, the site would reach 100% around July 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 October 2026

60%+10 pts

  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 1, 20 October 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 2, 20 October 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 3, 20 October 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 4, 20 October 2026

17 August 2026

50%+14 pts

  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 1, 17 August 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 2, 17 August 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 3, 17 August 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 4, 17 August 2026

3 June 2026

36%+12 pts

  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 1, 3 June 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 2, 3 June 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 3, 3 June 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 4, 3 June 2026

26 February 2026

24%+14 pts

  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 1, 26 February 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 2, 26 February 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 3, 26 February 2026
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 4, 26 February 2026

8 October 2025

10.0%+6.5 pts

  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 1, 8 October 2025
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 2, 8 October 2025

4 June 2025

3.5%+3.5 pts

  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 1, 4 June 2025
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 2, 4 June 2025
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 3, 4 June 2025
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 4, 4 June 2025

4 February 2025

0%+0.0 pts

  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 1, 4 February 2025
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 2, 4 February 2025
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 3, 4 February 2025

9 September 2024

0%

  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 1, 9 September 2024
  • Cove Edition Residence 2 By Imtiaz construction site, inspection photo 2, 9 September 2024

All 49 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Imtiaz Real Estate Investment & Development has 11 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Cove Edition Residence 2 By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cove Edition Residence 2 By Imtiaz handover date?
The registered completion date was October 2026, and the register still lists Cove Edition Residence 2 By Imtiaz as under construction. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Cove Edition Residence 2 By Imtiaz?
Cove Edition Residence 2 By Imtiaz was 60% built at the site inspection on 20 October 2026. The site has been inspected 8 times since September 2024. The Land Department took 49 site photos at its inspections.
Is Cove Edition Residence 2 By Imtiaz delayed?
Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
Who is building Cove Edition Residence 2 By Imtiaz?
The registered developer is Imtiaz Real Estate Investment & Development. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Cove Edition Residence 2 By Imtiaz?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.